Inspections for the day of: Wednesday, December 10, 2014.
Number of inspections: 7
Percentage of inspections complete: 86 %
Percentage of inspections not complete: 14 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-01666 FIRE-Final Inspection12/2/201412/3/2014 A 
Chad Phone #: ###-####
FIR14-00858 INSP-Sprinkler Rough-in12/9/201412/10/201412/10/2014 5:08:12 PMPPART
UG fire supply line including the IBR okayed for bury. Thrust blocking poured while on site.
BLD14-03194 FIRE-Final Inspection12/9/201412/10/201412/10/2014 3:55:08 PMPPASS
Fire life safety inspection completed acceptable.
FIR14-00887 INSP-Sprinkler Rough-in12/10/201412/10/201412/10/2014 3:33:15 PMPPART
UG fire supply line from the property line to the IBR approved for bury. Plans dated and initialed.
FIR14-00809 INSP-Final Inspection12/9/201412/10/201412/10/2014 2:29:44 PMPPASS
Fire alarm work completed and passed functional testing. Permit finaled.
BLD13-03405 FIRE-Sprinkler Rough-in12/10/201412/10/201412/10/2014 12:52:59 PMADONE
Rough-in at tower one 5th floor 531-537
FIR14-00196 INSP-Final Inspection12/9/201412/10/201412/10/2014 12:51:42 PMAPASS
Final walkthrough completed. Need to adjust one pendent head at the dining area, replace missing escutcheon at the basement level rec room. Flow testing passed. Permit finaled.