Inspections for the day of: Wednesday, August 5, 2015.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-00681 FIRE-Final Inspection8/5/20158/5/20158/5/2015 3:58:10 PMPPART
Final fire life-safety inspection for apartment building. Tested some new exit signs added to clarify egress paths in some areas. Also retested some emerg. lights that were not working last visit. Tested last dry pipe fire sprinkler system, that failed last test. All fire sprinklers are fully tested, however some systems are still shutdown as some painted heads have to be changed out. The fire alarm system has been fully tested however, it is not being monitored off-site because of the fire sprinkler work being done.
I have approved TCO for staff only personel to work in the leasing office only. I have not approved TCO for any use of the building for public use, access for residents, or for any overnight stays.
FIR14-00815 INSP-Final Inspection8/5/20158/5/20158/5/2015 3:51:25 PMPPART
Pre-final inspection for fire sprinkler systems. All systems have been fully tested and are operational. Left contractor with a punchlist of minor items (mostly escutcheons missing). Also some of the wet systems are still shut down as some painted heads need to be changed out.
Will reshedule final inspection when all work is completed.
FIR14-00887 INSP-Sprinkler Rough-in/Hydro8/4/20158/5/20158/5/2015 12:12:30 PMAPASS
Hydrostatic test of FS U/G supply line from city connection to BOR stub up.
200 psi @ 2 hours - PASSED
Also conducted flush test of this same supply line - flushed clear after 2 attempts.
OK to connect to A/S BOR.
FIR14-00603 INSP-Sprinkler Rough-in8/4/20158/5/20158/5/2015 12:09:49 PMAPASS
Retest of dry pipe system #1 for the north side parking garage.
PASSED - tripped within 58 seconds to waterflow.