Third Notice | | 3/16/2019 | 4/8/2019 | | DONE |
|
|
|
emailed to Paul 4/8/19
|
Second Notice | | 2/17/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12-19
|
First Notice | | 2/9/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
BLD-Final | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Jim Storey
|
|
|
Chris ###-####
|
DOC - Permit Finaled | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed for the bike shelter
Dave Phone #: ###-####
|
Print Occupancy Form | | | 1/30/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/30/2019 | | DONE |
|
|
|
|
BLD-Final | 1/29/2019 | 1/29/2019 | 1/29/2019 | P | NR |
Jim Storey
|
|
|
Dave Phone #: ###-#### need fire
|
BLD-Final | 1/28/2019 | 1/28/2019 | 1/29/2019 | P | NR |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/3/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 10/3/2018 | 10/3/2018 | 10/22/2018 | | DONE |
Julie Romig
|
|
|
10/16 (5wks) - 502 Micron Bike Shelter
|
Routing - PLAN CHECK | 10/3/2018 | | 10/22/2018 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 10/3/2018 | | 10/22/2018 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 10/22/2018 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2018 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 10/22/2018 | | DONE |
Julie Romig
|
|
|
Followed up with Dave Haugland at AHJ engineers regarding note: " Footing reinforcement on plans does not meet bottom reinforcement shown in calcs, but assumed engineer deemed it adequate since stress is low". Per Dave, the design works structurally, even though the footing design does not match the calcs. Ideally, the drawings and calcs would match, but since it works, Dave felt comfortable passing the structural design.
|
Permit Ready to Issue | | | 10/22/2018 | | DONE |
|
|
|
Need
GC Form
|
Routing - FIRE | 10/3/2018 | 10/3/2018 | 10/5/2018 | | PASS |
Erika Akin
|
|
|
U occupancy. Hydrants, access and fire flow checked. No impact to exisitng FD access. No comments attached.
|
Routing PW Drainage | 10/3/2018 | | 10/4/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 10/3/2018 | | 10/4/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2018 | | 10/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 10/3/2018 | | 10/3/2018 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC18-00006 for site.
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2018 | | DONE |
|
|
|
|
Routing PW Street Lights | 10/3/2018 | | 10/3/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 10/3/2018 | | 10/3/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Design Review | 10/3/2018 | | 10/3/2018 | | PASS |
Andrea Tuning
|
|
|
DRH18-00184 Andrea
|
Intake Approval | | | 10/1/2018 | | PASS |
|
|
|
|
Application received | | | 9/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 12 2018 1:29PM
|