FIR15-00408
| INSP-Sprinkler Rough-in | 10/9/2015 | 10/12/2015 | 10/12/2015 3:49:55 PM | A | PART |
|
|
Areas inspected, office/showroom area south of service bay, rough to cover inspection performed, inspected areas approved for cover. Main entry grid portion still needs inspection, grid was not installed at time of inspection. Drive thru bays on west side of building need rough to cover inspection performed before ceiling tile can be installed.
|
BLD14-03039
| FIRE-Conference | 10/12/2015 | 10/12/2015 | 10/12/2015 2:47:35 PM | P | DONE |
|
|
Fire conference complete
|
FIR15-00702
| INSP-Sprinkler Rough-in | 10/12/2015 | 10/12/2015 | 10/12/2015 2:09:28 PM | P | PASS |
|
|
Rough to cover inspection for the hard lids passed/complete, approved for cover.
|
FIR15-00690
| INSP-Sprinkler Rough-in | 10/12/2015 | 10/12/2015 | 10/12/2015 11:02:56 AM | P | PASS |
|
|
Rough to cover inspection passed/complete, approved for cover.
|
FIR15-00674
| INSP-Final Inspection | 10/9/2015 | 10/12/2015 | 10/12/2015 8:55:07 AM | A | PASS |
|
|
Final fire alarm inspection passed/complete
|