FIR16-00502
| INSP-Sprinkler Rough-in | 10/25/2016 | 10/25/2016 | 10/25/2016 3:07:12 PM | P | PASS |
|
|
Overhead hydro test passed for the new piping added.
|
BLD16-02895
| FIRE-Final Inspection | 10/25/2016 | 10/25/2016 | 10/25/2016 2:08:01 PM | P | FAIL |
|
|
Inspection was actually for a conference. Multiple exit signs and emergency lights need repaired and or added. Need correct occupant load signs, need project related fire alarm and fire sprinkler permits finaled. Could not find a hood suppression permit.
|
FIR16-00624
| INSP-Final Inspection | 10/24/2016 | 10/25/2016 | 10/25/2016 1:28:50 PM | A | PASS |
|
|
permit finaled
|
FIR16-00440
| INSP-Sprinkler Rough-in | 10/24/2016 | 10/25/2016 | 10/25/2016 9:46:02 AM | A | PART |
|
|
Rough-in passed. Tenting failed. No piping to be covered until the tenting inspection passes.
|
FIR16-00538
| INSP-Sprinkler Rough-in | 10/24/2016 | 10/25/2016 | 10/25/2016 9:44:44 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
|
BLD16-03768
| FIRE-Final Inspection | 10/24/2016 | 10/25/2016 | 10/25/2016 8:58:38 AM | A | PASS |
|
|
Life safety passed
|