FIR08-00550
| FIR-Aging Inspection | 10/26/2016 | 10/26/2016 | 11/1/2016 9:41:33 AM | | NR |
|
|
I turned this over to the fire dept for follow up
|
FIR16-00623
| INSP-Final Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 3:04:42 PM | P | PASS |
|
|
Permit finaled
|
BLD16-02802
| FIRE-Final Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 2:49:20 PM | P | PASS |
|
|
Life safety passed
|
BLD16-02895
| FIRE-Final Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 2:11:16 PM | P | CANC |
|
|
Not ready for a final yet due to project related fire alarm and fire sprinkler permits and corrections for life safety
|
FIR16-00502
| INSP-Final Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 2:02:11 PM | P | FAIL |
|
|
Need to pass the forward flush as discussed.
|
FIR16-00629
| INSP-Final Inspection | 10/25/2016 | 10/26/2016 | 10/26/2016 2:01:39 PM | A | FAIL |
|
|
Provide city approved plans, provide power supply for dialer in conduit. All devices tested ok.
|
FIR16-00672
| INSP-Sprinkler Rough-in | 10/26/2016 | 10/26/2016 | 10/26/2016 11:37:07 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
|
BLD16-01385
| FIRE-Final Inspection | 10/25/2016 | 10/26/2016 | 10/26/2016 10:35:07 AM | A | FAIL |
|
|
Project is not ready for a final inspection. I met with the general contractor and went over required life safety requirements to get this building signed off while others are unfinished. The biggest issue will be fire dpt access. I degerred him to Scott for temporary approval of fire lanes.
Jake Phone #: ###-####
|
BLD16-01389
| FIRE-Final Inspection | 10/25/2016 | 10/26/2016 | 10/26/2016 10:34:42 AM | A | FAIL |
|
|
Project is not ready for a final inspection. I met with the general contractor and went over required life safety requirements to get this building signed off while others are unfinished. The biggest issue will be fire dpt access. I degerred him to Scott for temporary approval of fire lanes.
Jake Phone #: ###-####
|
BLD16-01388
| FIRE-Final Inspection | 10/25/2016 | 10/26/2016 | 10/26/2016 10:34:10 AM | A | FAIL |
|
|
Project is not ready for a final inspection. I met with the general contractor and went over required life safety requirements to get this building signed off while others are unfinished. The biggest issue will be fire dpt access. I degerred him to Scott for temporary approval of fire lanes.
Jake Phone #: ###-####
|