ELE18-01206
| Electrical Rough-In | 11/6/2018 | 11/6/2018 | 11/6/2018 3:09:04 PM | P | PASS |
|
|
Please call Bryant for inspection of stair 1. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed ok to cover
|
ELE18-03602
| Final | 11/6/2018 | 11/6/2018 | 11/6/2018 1:38:11 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Christian Gelok Final ok
|
ELE18-04287
| Electrical Rough-In | 11/6/2018 | 11/6/2018 | 11/6/2018 12:14:04 PM | P | PASS |
|
|
panel inspection for small solar array please call Joziah at ###-#### when this inspection is up next. There are only four panels so he will likely leave when he''s done. He will go back and meet you if he has left. Phone #: ###-#### Inspection requested via web by Ryan King Power for Solar water heater. Paperwork onsite. Listing ok
|
ELE18-03451
| Final | 11/6/2018 | 11/6/2018 | 11/6/2018 11:18:24 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brad Girard final ok
|
ELE18-00835
| Electrical Rough-In | 11/5/2018 | 11/6/2018 | 11/6/2018 9:52:49 AM | A | PASS |
|
|
Al Phone #: ###-#### Bed, Bath, Hall and laundry area only ok to cover
|
ELE18-04109
| Electrical Rough-In | 11/5/2018 | 11/6/2018 | 11/6/2018 9:23:19 AM | A | PASS |
|
|
Taylor Barton " ###-####" Phone #: ###-#### Inspection requested via web by BRS Permitting Listing only ok
|
ELE18-04127
| Final | 11/5/2018 | 11/6/2018 | 11/6/2018 8:57:53 AM | A | NR |
|
|
Please inspect for final. Phone #: ###-#### Inspection requested via web by Chris Weimar BLD18-03987 Building permit not issued at time of Electrical inspection. All equipment has been check. Electrical permit ready to final after building permit is issued.
|