Inspections for the day of: Tuesday, November 6, 2018.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-02477 FIRE-Conference11/6/201811/6/201811/6/2018 3:15:47 PMPDONE
I spoke to Cody about needing more clearance for the FDC. I have involved Ron with the Boise Fire Dept with this issue.
FIR18-00628 INSP-Final Inspection11/6/201811/6/201811/6/2018 2:20:54 PMPPASS
Permit finaled
FIR18-00675 INSP-Sprinkler Rough-in/Hydro11/5/201811/6/201811/6/2018 2:07:04 PMPPART
Rough in for the underground supply line passed and the piping can be covered./ The Hydro for underground dedicated fire main failed due to visible loss at the guage.. Contact is Cesar Rodriguez Phone #: ###-#### Inspection requested via web by Brett Lawatch
FIR18-00420 INSP-Sprinkler Rough-in11/5/201811/6/201811/6/2018 1:25:02 PMAPASS
5th floor bathroom and Lobby, see marked approved plans, piping is ok to cover.
FIR17-00708 FIR-Aging Inspection11/5/201811/6/201811/6/2018 12:33:38 PMAFAIL
Rings have been provided around the pendant heads which need approval from the manufacture. Need warning signs at the riser as per the approved plans. Flow switch functioned and rang the outside alarm bell.

Todd Phone #: ###-####
FIR18-00686 INSP-Sprinkler Rough-in11/5/201811/6/201811/6/2018 12:29:23 PMAFAIL
See the city approved plans for locations/rooms in the east half of the basement that was inspected today. As-builts are required, approval is needed for supplying the pendants in the corridor from a 1 1/2" branchline instead of the 3" main, verification is needed for combustible concealed spaces above the ceiling as discussed, need verification of spacing of sidewall heads from the walls they are installed against, need branchline restraints, need earthquake bracing installed, need flat faced bushing changed.

Basement // Ron Phone #: ###-####
BLD18-02924 FIRE-Final Inspection11/5/201811/6/201811/6/2018 11:29:10 AMAPASS
Life safety passed

Phone #: ###-#### Inspection requested via web by Rick Reynolds
FIR18-00702 INSP-Final Inspection11/5/201811/6/201811/6/2018 11:28:35 AMAPASS
Permit finaled

Rick Phone #: ###-####
NAF18-00050 INSP-Supply line flush11/2/201811/6/201811/6/2018 10:24:07 AMAPASS
The underground supply piping flush passsed
FIR18-00486 INSP-Final Inspection11/5/201811/6/201811/6/2018 10:05:35 AMAPASS
Permit finaled
FIR18-00311 INSP-Sprinkler Rough-in11/5/201811/6/201811/6/2018 9:38:59 AMPCANC
Tenting inspection Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
FIR18-00311 INSP-Sprinkler Rough-in/Hydro11/5/201811/6/201811/6/2018 9:38:53 AMACANC
Call Anthony before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
BLD18-00974 FIRE-Final Inspection11/5/201811/6/201811/6/2018 8:02:40 AMAPASS
Life safety passed. Exit sign to be installed in warehouse prior to the building inspection as discussed.

Cody Phone #: ###-####
FIR18-00570 INSP-Final Inspection11/5/201811/6/201811/6/2018 7:59:04 AMAPASS
Permit finaled

Phone #: ###-#### Inspection requested via web by Ken Webster
FIR18-00738 INSP-Sprinkler Rough-in/Hydro11/5/201811/6/201811/6/2018 7:24:25 AMPCANC
UG Hydro for 8" service. Please call Troy With time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
FIR18-00410 INSP-Final Inspection10/30/201811/6/201811/6/2018 12:00:00 AMACANC
Hi Jim If possible we would like to start the inspection at 7:00 am. Would you please call and let me know if that is doable? Thanks Mike Timmerman Phone #: ###-#### >> Inspection requested via web by Neal Timmerman

Mike will schedule a new date with the owner, as they need an early start and time to plan. Expecting Wednesday or Thursday morning at 7:00 am.
FIR18-00436 INSP-Final Inspection11/5/201811/6/201811/6/2018 12:00:00 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Gary Gambino

All functioned properly. Smoke detector on stairwell side of Won Door should have been originally installed but was approved without.
FIR18-00733 INSP-Final Inspection11/5/201811/6/201811/6/2018 12:00:00 AMACANC
Please call 1/2 hour before arriving. Thanks Phone #: ###-#### >> Inspection requested via web by david davis

Rescheduling for 8:00 am Wednesday morning.
FIR18-00515 INSP-Final Inspection11/5/201811/6/201811/6/2018 12:00:00 AMACANC
Please call 1/2 hour before arriving. Thanks Phone #: ###-#### >> Inspection requested via web by david davis.

Rescheduling for 8:00 am Wednesday morning.
FIR18-00683 INSP-Final Inspection11/5/201811/6/201811/6/2018 12:00:00 AMACANC
Dave Phone #: ###-####

Rescheduling for 8:00 am Wednesday morning.