BLD16-03730
| BLD-Final | 11/4/2016 | 11/7/2016 | 11/10/2016 8:01:34 AM | A | PASS |
|
|
Jenna Phone #: ###-####
|
BLD16-03346
| BLD-Footing | 11/7/2016 | 11/7/2016 | 11/8/2016 11:42:57 AM | P | NR |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD16-01125
| BLD-Other | 11/7/2016 | 11/7/2016 | 11/8/2016 11:42:57 AM | P | PASS |
|
|
Scott// exterior stairs Phone #: ###-#### Exterior stairs....OK
|
BLD16-01040
| BLD-Wall Bracing | 11/4/2016 | 11/7/2016 | 11/8/2016 11:42:56 AM | P | PART |
|
|
Dave Phone #: ###-#### No bracing to look at yet, but OK to cover East, South and West exterior wall on the outside.
|
BLD16-01125
| BLD-Framing/Rough-in | 11/7/2016 | 11/7/2016 | 11/7/2016 3:51:25 PM | P | FAIL |
|
|
Stairs // Chris Phone #: ###-#### Called for stair inspection. Contractor has been remodeling and adding to stairs to meet Minimum code for rise and run......C/N posted for headroom clearance per R-311.7.2 2012 IRC.
|
BLD16-03205
| BLD-Ceiling Grid Inspection | 11/7/2016 | 11/7/2016 | 11/7/2016 1:51:52 PM | P | PASS |
|
|
Barry Phone #: ###-####
|
BLD16-03213
| BLD-Foundation | 11/4/2016 | 11/7/2016 | 11/7/2016 1:51:37 PM | P | PASS |
|
|
Dane Phone #: ###-####
|
BLD16-03435
| BLD-Framing/Rough-in | 11/7/2016 | 11/7/2016 | 11/7/2016 1:51:16 PM | P | PASS |
|
|
Kelly Phone #: ###-####
|
BLD15-03093
| BLD-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 1:50:43 PM | P | DONE |
|
|
Work in progress.
|
BLD16-02731
| BLD-Energy code compliance | 11/4/2016 | 11/7/2016 | 11/7/2016 12:00:46 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Christophe Heinz
|
BLD15-00048
| BLD-Wall cover | 11/4/2016 | 11/7/2016 | 11/7/2016 11:50:47 AM | A | PASS |
|
|
Call 15 minutes before // Scott Phone #: ###-#### Resubmittal for non rated wall to replace 1hr wall.....OK. Insulation OK and all framing OK.
|
BLD16-04025
| BLD-Final | 11/4/2016 | 11/7/2016 | 11/7/2016 10:55:31 AM | A | PASS |
|
|
Please call me if you would like me to meet you onsite with plans. Solar Array installed to spec. Must walk around to back yard to see array. Phone #: ###-#### Inspection requested via web by Matthew Dunay
|
BLD16-04025
| DOC - Permit Finaled | 11/7/2016 | 11/7/2016 | 11/7/2016 10:55:17 AM | P | PASS |
|
|
|
BLD15-03093
| BLD-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 10:25:16 AM | A | DONE |
|
|
WIP.
|
BLD16-01291
| BLD-Energy code compliance | 11/4/2016 | 11/7/2016 | 11/7/2016 10:17:42 AM | A | PART |
|
|
Jake Phone #: ###-#### Firestop penitrations 3 hr wall.
|