Inspections for the day of: Tuesday, February 25, 2020.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-03898 FIRE-Final Inspection2/25/20202/25/20202/25/2020 3:07:56 PMPPART
A temporary for life safety is being given for 90 days. A final life safety can be given when the project related fire alarm permit is finaled.

Phone #: ###-#### Inspection requested via web by Nate Carriveau
FIR19-00883 INSP-Final Inspection2/25/20202/25/20202/25/2020 3:06:52 PMPPART
A temporary for this permit has been given for 90 days. To final this permit the new notification devices need to sync with the existing notification devices as per NFPA 72.

Contact is Dirk. Building has been tested and verified for synchronization. Phone #: ###-#### Inspection requested via web by Morgan Ahten
BLD19-02982 FIRE-Final Inspection2/25/20202/25/20202/25/2020 3:05:21 PMPPASS
Life safety passed.

Jose Phone #: ###-####
BLD20-00103 FIRE-Final Inspection2/25/20202/25/20202/25/2020 12:36:01 PMPPASS
Life safety passed. The fire alarm system that had been installed without a permit has been removed.

Final inspection request. Phone #: ###-#### Inspection requested via web by Jason Richardson
FIR19-00770 INSP-Sprinkler Rough-in/Hydro2/25/20202/25/20202/25/2020 12:18:32 PMPPASS
Overhead hydro witnessed with no pressure loss.

Cole will be the contact. Please give him an hours notice to meet you there. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD20-00284 FIRE-Final Inspection2/24/20202/25/20202/25/2020 11:57:55 AMAPASS
Life safety passed.

call for access- Christina Phone #: ###-####
FIR19-00831 INSP-Sprinkler Rough-in2/24/20202/25/20202/25/2020 10:32:40 AMAPASS
Rough-in passed. Need to add one 4 way brace and possible additional branchline bracing as discussed. No piping to be covered until additional rough-in inspection has been scheduled.

Johnathon Phone #: ###-####
FIR19-00816 INSP-Sprinkler Rough-in2/24/20202/25/20202/25/2020 10:02:39 AMAPASS
Rough-in and tenting passed for the south half of tower 3. Piping is ok for cover. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
BLD20-00443 FIRE-Final Inspection2/24/20202/25/20202/25/2020 7:49:32 AMAPASS
life safety passed.


Matt Phone #: ###-####