Inspections for the day of: Thursday, February 28, 2019.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBrian Scoles
TitleMEC INSPECTOR
Phone #914-4915
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-00861 Final2/28/20192/28/20192/28/2019 3:46:23 PMPPASS
final ok- tagged gas line at meter location
MEC19-00861 Pressure Test2/28/20192/28/20192/28/2019 3:45:31 PMPPASS
Inspection requested via web by Floyd Floyd Peek- 20lb gas pass to mobile home- ok to backfill
MEC19-00862 Pressure Test2/28/20192/28/20192/28/2019 3:27:00 PMPNR
Inspection requested via web by Floyd Floyd Peek- this inspection was completed by i ntermountain gas, they pulled pressure gauge off- i talked with intermountsain gas- they will remove meter so a pressure test will need completed again- I talked with Max about this he is aware
MEC19-00809 Final2/25/20192/28/20192/28/2019 2:49:08 PMPPASS
INSTALLER TRAVIS ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- furnace a/c coil co ok
MEC19-00725 Rough-in2/27/20192/28/20192/28/2019 2:49:08 PMPFAIL
Please call Dan on your way. ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks- need to submit manual j to city and have aopproved manual j onsite for inspection- all exhaust fans need to be ran per approved prints per detail A- left correction notice first floor window
MEC18-04832 Conference2/27/20192/28/20192/28/2019 12:32:34 PMAFAIL
witness duct blast test at 1130- ###-####- north unit duct blast test pass- south unit failed-reschedule test with me day in advance
MEC18-04831 Final2/28/20192/28/20192/28/2019 11:44:38 AMAPASS
final ok
MEC18-04831 Conference2/27/20192/28/20192/28/2019 11:44:18 AMAPASS
duct blast witness at 11 am- ###-####- final ok- duct blast test pass both units
MEC18-04954 Final2/26/20192/28/20192/28/2019 11:08:35 AMAPASS
Phone #: ###-#### Inspection requested via web by Marisa Hone- furnace only co ok-
MEC18-04861 Final2/28/20192/28/20192/28/2019 10:54:17 AMAPASS
FLUE TEST AND FINAL- 1030am- furnace only co ok- 5lb flue test pass
MEC18-04954 Pressure Test2/26/20192/28/20192/28/2019 10:13:43 AMAPASS
Phone #: ###-#### Inspection requested via web by Marisa Hone- 5lb flue test pass
MEC19-00827 Final2/26/20192/28/20192/28/2019 9:17:07 AMAPASS
Phone #: ###-#### Inspection requested via web by Marisa Hone- a/c only co ok
MEC18-02419 Mec-Aging Inspection2/28/20192/28/20192/28/2019 8:47:25 AM FAIL
called contractor to have them schedule final if they did work- they will check into this per phone call
MEC19-00735 Rough-in2/27/20192/28/20192/28/2019 8:43:31 AMAFAIL
Phone #: ###-#### Inspection requested via web by Ashley Shoecraft- 4" fresh duct missing 3 screws in some connections- all joints need secured with 3 screws minimum
MEC19-00736 Rough-in2/27/20192/28/20192/28/2019 8:42:27 AMAPASS
Phone #: ###-#### Inspection requested via web by Ashley Shoecraft- fireplace R/I ok