Inspections for the day of: Tuesday, March 10, 2020.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00353 INSP-Sprinkler Rough-in/Hydro3/10/20203/10/20203/10/2020 3:20:20 PMPCANC
Please give me a call it will be for standpipe 2nd through 4th. as late in day as possible Phone #: ###-#### Inspection requested via web by jeremiah robison
FIR19-00816 INSP-Sprinkler Rough-in3/10/20203/10/20203/10/2020 1:36:23 PMPPART
Rough-in on towers three and four building 11 passed but the tenting failed due to piping that needs "boxed" in in locations in each apartment as discussed. Piping can be covered on the first and second floors. Piping can not be covered on third floor until tenting is modified. ]Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR19-00492 DOC - Permit Finaled3/10/20203/10/20203/10/2020 1:29:07 PMPPASS
permit finaled
BLD20-00388 FIRE-Final Inspection3/9/20203/10/20203/10/2020 12:42:26 PMAFAIL
The door hardware and the annual inspection for the fire sprinkler system is ok but the fire alarm panel is in trouble with a phone line 2 fault. Robert Phone #: ###-####
FIR19-00886 INSP-Sprinkler Rough-in3/9/20203/10/20203/10/2020 12:41:21 PMAPASS
See approved plans for additional heads marked ok in the hard lids where piping is ok for cover.
Tom Phone #: ###-####
FIR20-00106 INSP-Final Inspection3/10/20203/10/20203/10/2020 9:42:16 AMPCANC
Not ready due to the fire alrm interconnect not being complete. Nate Phone #: ###-####
FIR19-00511 INSP-Final Inspection3/10/20203/10/20203/10/2020 9:34:29 AMPPASS
Permit finaled.
BLD18-03695 FIRE-Final Inspection3/9/20203/10/20203/10/2020 9:32:22 AMAPASS
Life safety passed.

Mark Phone #: ###-####