ESC15-01138
| General Inspection | 3/20/2017 | 3/20/2017 | 3/22/2017 3:54:56 PM | | PASS |
|
|
WIP. No ESC issues observed.
|
ESC14-00657
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 4:26:29 PM | | PASS |
|
|
WIP on SFHs. Sub ok. No corrections.
|
ESC15-01391
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 3:50:29 PM | | CANC |
|
|
|
ESC15-01224
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 3:50:29 PM | | PASS |
|
|
Walk through with RP on site. Project nearing completion. Minimal earth disturbance. Perimeter of job site is clean. Concrete washout is full RP has maintenance scheduled. SWPPP inspections are up to date.
|
ESC17-00286
| Site Preparation | 3/20/2017 | 3/20/2017 | 3/20/2017 3:04:34 PM | P | PASS |
|
|
Met onsite with RP. Discussed concrete washout, trackout, keeping sidewalk and surroundings clean. Site has a 30-40ft vegetated buffer between the creek and a small buffer strip between the sidewalk and the disturbance. Oaky to start.
|
ESC16-00385
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 2:32:30 PM | P | PASS |
|
|
Soil not yet stable. Revegetation stage. project ok. No corrections requested.
|
ESC16-01654
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 2:20:54 PM | P | PASS |
|
|
Demolition in progress. No trackout. BMPs are maintained and ok. No corrections requested.
|
ESC16-00852
| Site Final | 3/20/2017 | 3/20/2017 | 3/20/2017 2:16:34 PM | P | PASS |
|
|
|
ESC16-00852
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 2:16:19 PM | P | PASS |
|
|
Project complete. Soil stable. Okay to final.
|
ESC15-01004
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 2:14:39 PM | | PASS |
|
|
No ESC issues observed.
|
ESC17-00066
| Site Preparation | 3/17/2017 | 3/20/2017 | 3/20/2017 1:54:49 PM | P | PASS |
|
|
DI bag installed, construction entrance installed, sign posted. Okay to start. Watch for trackout onto Boise Ave.
|
ESC14-00626
| Site Final | 3/20/2017 | 3/20/2017 | 3/20/2017 11:09:08 AM | A | PASS |
|
|
|
ESC14-00626
| Aging Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 11:08:45 AM | | PASS |
|
|
Vegetation complete. Soil stable. Okay to final
|
ESC16-00021
| Site Final | 3/20/2017 | 3/20/2017 | 3/20/2017 11:00:23 AM | P | PASS |
|
|
|
ESC16-00021
| Aging Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 11:00:04 AM | | PASS |
|
|
Project complete. Soil stable. Okay to final
|
ESC15-00378
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 10:58:50 AM | | PASS |
|
|
Vegetation phase. Vegetation has not reached 70% cover. Project ok.
|
ESC16-00406
| General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 10:25:09 AM | | PASS |
|
|
The ECBs are providing adequate soil stabilization. Vegetation has begun to establish over much of the hillsides throughout the subdivision. The scour area on 8th street extension has been stabilized with ECBs there is some sediment deposited on the top of the ECBs. Corrections: The Highlands Cover Rd. entrance needs to be sweep, the construction entrance needs maintenance, the DI bags need maintenance.
|