Inspections for the day of: Monday, March 30, 2020.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC19-01749 General Inspection3/27/20203/30/20204/2/2020 3:55:05 PMPFAIL
Trackout and dirty gutter on Alpine. No construction entrances

Follow up scheduled to see if they clean up...
ESC19-00082 General Inspection3/30/20203/30/20204/1/2020 3:18:46 PM PASS
WIP on frame. No onsite parking. No erosion or sediment runoff issue and BMPs are installed. Approved.
ESC18-01022 General Inspection3/30/20203/30/20203/31/2020 3:51:03 PMPPASS
.
ESC18-01767 Site Final3/27/20203/30/20203/31/2020 3:33:28 PMPPASS
ESC19-01656 Site Preparation3/27/20203/30/20203/31/2020 2:50:52 PMAPASS
BMPs installed. ESC permit sign posted. Need to change ESC permit into Matt Brown construction.

Site is in compliance. Approved for construction.
ESC18-01106 Aging Inspection3/30/20203/30/20203/30/2020 10:54:27 AM PASS
Work, disturbed area and materials confined to back yard. WIP, foundation & frame complete.
ESC19-01727 Conference3/30/20203/30/20203/30/2020 9:21:58 AMPDONE
Phone discussion about crews beginning grading on this phase this week. Site preparation inspection scheduled.

Access phase is through Barnwood #1, no new entrances to Lake Hazel or Cole. No adjacent surfaces waters or perimter BMPs other than staying within clearing limits.

Fugitive dust control will be top priority for ESC on this site.
ESC18-01432 General Inspection3/30/20203/30/20203/30/2020 8:20:35 AM CANC
ESC18-01482 Aging Inspection3/30/20203/30/20203/30/2020 8:15:58 AM CANC