Inspections for the day of: Monday, April 22, 2019.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBrian Scoles
TitleMEC INSPECTOR
Phone #914-4915
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-01634 Final4/22/20194/22/20194/22/2019 3:49:18 PMPPASS
Inspection requested via web by Margie Rowe- air handler heat pump ok
MEC19-01603 Pressure Test4/22/20194/22/20194/22/2019 3:03:26 PMPPASS
INSTALLER DOUG ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- 60lb gas pass tagged meter location- 20lb gas pass- need union after shutoff valve and sediment traps on both side of regultor- call in final when ready
MEC19-01576 Final4/18/20194/22/20194/22/2019 2:29:31 PMPPASS
INSTALLER ARCHIE ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- furnace in crawl co ok
MEC19-01551 Final4/19/20194/22/20194/22/2019 1:46:05 PMPPASS
Phone #: ###-#### Inspection requested via web by Marisa Hone- furnace a/c coil co o,
MEC18-04126 Final4/22/20194/22/20194/22/2019 1:12:23 PMPNH
Call greg for questions Phone #: ###-#### Inspection requested via web by Greg Mendiola
MEC19-01484 Rough-in4/22/20194/22/20194/22/2019 12:03:19 PMPPASS
Phone #: ###-#### Inspection requested via web by Gary Reeves- R/I ok
MEC19-01234 Rough-in4/19/20194/22/20194/22/2019 11:33:48 AMAPASS
Inspection requested via web by Mike Almanza- fireplace R/I ok
MEC19-01552 Final4/19/20194/22/20194/22/2019 10:58:10 AMAPASS
Phone #: ###-#### Inspection requested via web by Marisa Hone- furnace only co ok
MEC19-01553 Final4/19/20194/22/20194/22/2019 10:41:11 AMAPASS
Phone #: ###-#### Inspection requested via web by Aaron Alandt- furnace a/c coil co ok
MEC19-00467 Rough-in4/19/20194/22/20194/22/2019 10:18:32 AMAPASS
Ceiling cover. Call 20 minutes prior to Todd Phone #: ###-#### Inspection requested via web by Kim Adams- registers , flex and insulation ok- ok for ceiling tiles- smoke detectors installed in units- need insulation shield installed thru roof on unit heater by final
MEC19-01310 Final4/19/20194/22/20194/22/2019 9:42:32 AMAFAIL
Phone #: ###-#### Inspection requested via web by Marisa Hone- need co detector- need secondary drain off coil ran to floor or wet switch installed
MEC19-01505 Final4/16/20194/22/20194/22/2019 9:29:02 AMANH
Please call Louis Montano prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette- called number listed no answer- went by no one home-
MEC19-01184 Final4/19/20194/22/20194/22/2019 9:15:42 AMAPASS
Phone #: ###-#### Inspection requested via web by Marisa Hone- furnace a/c coil co ok
MEC19-01419 Final4/17/20194/22/20194/22/2019 8:50:09 AMAPASS
Water heater final is schedule same time -- Technician will be out doing a duct cleaning and will be able to give inspector access -Nolan ###-####-- Phone #: ###-#### Inspection requested via web by Justin Osterhout- furnace a/c coil co ok
MEC18-04126 Mec-Aging Inspection4/22/20194/22/20194/22/2019 8:34:27 AM FAIL
contractor needs to schedule final inspection- BLD permit still open
MEC18-04180 Mec-Aging Inspection4/22/20194/22/20194/22/2019 8:33:35 AM FAIL
contractor needs tpo schedule inspection if work was done- permit will expire 7-22-19 if no activity
MEC18-04153 Mec-Aging Inspection4/22/20194/22/20194/22/2019 8:32:40 AM FAIL
contractor needs to schedule inspection if work has been done- permit will expire 7-22-19 if no activity
MEC18-04157 Mec-Aging Inspection4/22/20194/22/20194/22/2019 8:31:46 AM CANC
MEC18-04157 Final4/22/20194/22/20194/22/2019 8:30:33 AMAPASS
MEC19-01575 Final4/19/20194/22/20194/22/2019 8:29:57 AMAPASS
Requests early AM if possible. Mike Vega ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette- a/c coil co ok
MEC19-01613 Pressure Test4/22/20194/22/20194/22/2019 8:12:14 AMAPASS
20lb gas pass underground- ok to backfill- call in final when everything hooked up