Inspections for the day of: Thursday, April 25, 2019.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-00498 General Inspection4/25/20194/25/20194/26/2019 4:13:03 PM PEND
No offsite discharges or issues observed. Grass on slopes is growing. Areas where ECBs were installed are growing, but tenting is occuring due to plants lifting up the blanket. Error could be installing blankets over the wattles prevent good contact with the soil.

Will follow up with operator on fixing damaged sections of silt fence, and installing additional check dams along the access road to the stormwater pond.

Follow up scheduled
ESC18-00462 General Inspection4/25/20194/25/20194/26/2019 2:33:54 PM PASS
Construction appears complete. BLD is still open. Disturbed area stabilized and landscaped. Temporary BMPs (wattles) have been removed. ESC permit finaled.
ESC18-00467 General Inspection4/25/20194/25/20194/25/2019 12:25:05 PM CANC
ESC17-00455 General Inspection4/25/20194/25/20194/25/2019 12:24:44 PM PEND
ESC16-01395 General Inspection4/25/20194/25/20194/25/2019 11:49:28 AM CANC
ESC16-00938 General Inspection4/25/20194/25/20194/25/2019 11:49:19 AM CANC
ESC18-00109 General Inspection4/25/20194/25/20194/25/2019 8:27:46 AM PASS
NO signigicant trackout. Project staying within clearing limits and surrounded by preserved vegetation. RP stated that the disturbed slope above the driveway cut will get another hydroseeding and landscaping is starting to occur. No corrections at this time.