ESC18-01390
| BMP Violation | 5/23/2019 | 5/28/2019 | 5/31/2019 8:21:02 AM | P | CANC |
|
|
|
ESC16-00778
| Site Final | 5/28/2019 | 5/28/2019 | 5/30/2019 7:46:20 AM | P | PASS |
|
|
|
ESC19-00123
| General Inspection | 5/23/2019 | 5/28/2019 | 5/29/2019 9:44:09 AM | A | PEND |
|
|
RP out of town. Says received messages about silt fence and will install upon return. Follow up scheduled
|
ESC16-00625
| Complaint Inspection | 5/23/2019 | 5/28/2019 | 5/29/2019 8:12:31 AM | A | PEND |
|
|
Report of clogged drainage pipe that runs under downhill homes on Danmore.
Investigation in progress. Notified ACHD and PW Hillside Drainage.
|
ESC18-01499
| Complaint Inspection | 5/23/2019 | 5/28/2019 | 5/29/2019 7:58:59 AM | A | FAIL |
|
|
uncontained concrete washout running off site
Warning issued to onsite crew to clean up and provide new washout
|
ESC18-01374
| Site Final | 5/28/2019 | 5/28/2019 | 5/28/2019 12:36:32 PM | P | PASS |
|
|
BLD finaled, home landscaped. No temporary BMPs to removed. ESC permit finaled.
|
ESC17-01245
| DOC - Permit Finaled | 5/28/2019 | 5/28/2019 | 5/28/2019 12:31:15 PM | P | PASS |
|
|
|
ESC18-01349
| Site Final | 5/28/2019 | 5/28/2019 | 5/28/2019 12:29:53 PM | P | PASS |
|
|
Home exterior complete, landscaped, and stabilized. Gutter downspouts installed. No ESC corrections, permit finaled.
|
ESC19-00076
| General Inspection | 5/28/2019 | 5/28/2019 | 5/28/2019 12:27:33 PM | P | FAIL |
|
|
Correction request: - clean up trackout on sidewalk and street at end of the day - add additional rock to construction entrance to increase entrance length to a minimum of 50 ft.
|
ESC19-00443
| General Inspection | 5/28/2019 | 5/28/2019 | 5/28/2019 12:15:09 PM | P | FAIL |
|
|
Corrections needed:
- clean up dumped washout - provide washout for future washwaters of cement, paint, stucco - change out storm drain sediment protection
|
ESC18-01020
| BMP Violation | 5/24/2019 | 5/28/2019 | 5/28/2019 11:37:29 AM | A | PASS |
|
|
Fees from 3/27 paid, site reinspection never completed.
No violations at site. Dumped washout and loose trash cleaned up. No one currently parking in the mud. Fees have been paid, parcel hold removed
|
ESC18-01266
| BMP Violation | 5/24/2019 | 5/28/2019 | 5/28/2019 11:37:06 AM | A | PASS |
|
|
Fees from 3/27 paid, site reinspection never completed.
No violations at site. Dumped washout and loose trash cleaned up. No one currently parking in the mud. Fees have been paid, parcel hold removed
|
ESC18-01021
| General Inspection | 5/28/2019 | 5/28/2019 | 5/28/2019 11:36:04 AM | P | PASS |
|
|
Needs final landscaping and stabilization. Home is occupied.
|
ESC18-01531
| General Inspection | 5/28/2019 | 5/28/2019 | 5/28/2019 11:28:30 AM | P | FAIL |
|
|
Corrections needed:
- install perimeter sediment controls down slope from project along sidewalk and lot line to prevent muddy runoff onto sidewalks - have trash emptied - address significant erosion and slope damage behind home and below deck footings. Steep slopes should be protected with erosion control blankets after repair. RP stated they are going to install temporary gutters
|
ESC17-00842
| General Inspection | 5/28/2019 | 5/28/2019 | 5/28/2019 11:24:18 AM | P | FAIL |
|
|
Silt fences at top of culdesac have not been repaired as previously requested over the last month. Final warning request.
Corrections: - clean up sidewalks - replace silt fence that is damaged at top of culdesac - do maintenance on storm drain sediment bags
|
ESC18-01680