Inspections for the day of: Tuesday, May 29, 2018.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00141 INSP-Sprinkler Rough-in5/23/20185/29/20185/30/2018 1:47:08 PMPCANC
Wrong building was scheduled.

Colton Cox is the contact for this rough-in on 6 units. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-00976 FIRE-Final Inspection5/29/20185/29/20185/30/2018 10:41:18 AMPPASS
Life safety passed

Phone #: ###-#### Inspection requested via web by Will Thomason
FIR18-00411 INSP-Sprinkler Rough-in5/23/20185/29/20185/30/2018 8:29:32 AMPPASS
Rough-in passed for Units 107, 207, 307, 108, 208, 308. A plan mod will be needed showing the changes in the remote area and pipe routing changes in the other Units.

Colton Cox is the contact for this rough-in on 6 units. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00064 INSP-Sprinkler Rough-in5/29/20185/29/20185/29/2018 3:38:20 PMPPASS
Rough-in for the drops passed. Piping can be covered. Protection has been provided under overhead door.

Call Anthony to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR16-00708 INSP-Final Inspection5/25/20185/29/20185/29/2018 1:46:40 PMAFAIL
Today was a partial inspection. We verified that all off the redlined corrections had been made and are shown on the plan modification. The two items that had been missed was the data sheet approved did not match the fire alarm control panel installed and the dialer was not approved/shown. When these two items have been approved we can begin testing of the devices.


Nick Tank, inspecting technician, building is open access Phone #: ###-#### Inspection requested via web by Rose Peterson
BLD17-01937 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:56:07 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02007 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:55:47 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02006 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:55:28 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02008 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:55:11 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02009 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:54:51 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02010 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:54:24 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02011 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:54:07 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02012 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:53:50 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02013 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:53:32 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02015 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:53:08 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project
Please call ahead for access - Steve Phone #: ###-####
BLD17-02016 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:52:43 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02017 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:49:46 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
BLD17-02014 FIRE-Final Inspection5/23/20185/29/20185/29/2018 12:48:56 PMAFAIL
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project.



Please call ahead for access - Steve Phone #: ###-####
BLD18-00074 FIRE-Final Inspection5/25/20185/29/20185/29/2018 9:07:12 AMAFAIL
Missing all of the small documents. I did a quick walk through and the typical life safety items appear to be ok.


George Phone #: ###-####