Inspections for the day of: Monday, July 17, 2017.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00731 General Inspection7/17/20177/17/20177/18/2017 1:29:44 PM PASS
WIP. Trash contained. silt fence ok. No trackout
ESC16-00989 General Inspection7/14/20177/17/20177/18/2017 10:48:36 AMAPASS
WIP on interior and exterior. Weeds have partially stablized the hillside. No runoff. No trackout. Trash contained. No dust issues observed.
ESC13-00524 General Inspection7/17/20177/17/20177/18/2017 10:47:33 AM PEND
Utility trenching in progress. Area where the dirt from the trenching is located needs to be swept up after the trenches are backfilled.
No dust. No trackout. Trash is contained.
ESC15-00541 General Inspection7/14/20177/17/20177/18/2017 10:45:38 AMAPASS
WIP on SFHs some interior trackout. Trash contained.
ESC13-01273 Aging Inspection7/17/20177/17/20177/18/2017 10:09:18 AM PASS
Project complete. Okay to final.
ESC15-00729 General Inspection7/17/20177/17/20177/17/2017 4:04:25 PMPPASS
WIP on main road drainage system and manholes. WIP on SFHs. Some trackout, trash is contained, no dust issues observed. No corrections requested.
ESC17-00540 General Inspection7/17/20177/17/20177/17/2017 3:11:58 PMPPASS
ESC16-01733 General Inspection7/17/20177/17/20177/17/2017 3:11:46 PMPPASS
Nearly ready for site final. Small area not landscaped and trash container still on site. Scheduled site final for next Monday.
ESC16-00914 General Inspection7/17/20177/17/20177/17/2017 3:09:44 PM PASS
ESC17-00194 General Inspection7/10/20177/17/20177/17/2017 3:09:32 PMAPASS
Mixer has been removed. Trash has been picked up.
ESC17-00013 General Inspection7/17/20177/17/20177/17/2017 2:32:46 PMPPART
Need to clean up trackout and refresh entrance/exit. Silt fence needs minor repairs.

Corrections are also noted in the SWPPP. SWPPP inspections are up to date. some stockpiles are still on site.

No WIP at time of inspections. No fugitive dust or wind blow trash.
ESC17-00018 General Inspection7/17/20177/17/20177/17/2017 1:57:18 PMPPASS

WIP on grading for roads, creating fill dirt, and leveling stockpiles. The drainage to the East of the site along Eckert road is revegetating.
Perimeter silt fence is in place and ok.

No dust control on site no fugitive dust during time of inspection. Will inform RP to have dust control ready.

No more dewatering is anticipated. The check dams and any other dewatering BMPs should be removed from the land west of the site.

No trackout and trash is contained.
ESC16-00822 General Inspection7/17/20177/17/20177/17/2017 1:08:10 PM PASS
Interior and exterior WIP. Trash contained. No trackout. No corrections issued.
ESC17-00774 Conference7/17/20177/17/20177/17/2017 1:06:58 PMAPASS
Pre-construction meeting:

Call in site preparation inspection before work begins and after BMPs are installed ###-####

Sign will be located on old hickory by the job site trailer. The SWPPP plan is located on Old Hickory as well. Site meetings are held on Wednesdays at 9:00AM in the job trailer.

Ensure use of dust control during the stripping and excavation phase which will begin next week. Comply with all other ESC requirements for City of Boise and EPA as well.

Dewatering:
Dewatering will take place. The excavator plans to strip the land first, dig test pits to determine the GW level, and then begin dewatering. The plan is to let the water sheet flow into the field across warm springs. This section of road will be closed during this time.

Call in an inspection to City of Boise before dewatering beings and after the dewatering set up is in place. This is to ensure the set up matches the approved plan and to reduce the chance of stopping the dewatering once it is underway if a change does need to be made.

Revegetation/stabilization:
Will be occurring during August and September. Supplemental irrigation will be installed and used to establish the vegetation. The channel will be lined with rip rap for stabilization.
ESC16-01561 General Inspection7/17/20177/17/20177/17/2017 11:53:08 AMPPASS
Grading is complete. curb and street are installed. No dust, no trackout, trash contained. No corrections requested.
ESC16-01650 General Inspection7/17/20177/17/20177/17/2017 9:50:25 AMPPASS
Grading is complete. Curb and paving are complete. No dust, no trackout, trash contained. No corrections issued.
ESC15-00556 General Inspection7/17/20177/17/20177/17/2017 9:35:38 AM PASS
WIP on SFH. Trash is contained. Streets are clean, no trackout. Concrete washout ok and in use. Signs are posted. DIs okay. No corrections requested.
ESC16-00936 General Inspection7/17/20177/17/20177/17/2017 8:04:34 AMPCANC
ESC16-00935 General Inspection7/10/20177/17/20177/17/2017 8:04:26 AMACANC