Inspections for the day of: Thursday, July 30, 2015.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00360 General Inspection7/30/20157/30/20157/31/2015 11:12:15 AM PASS
Yard is now landscaped and stabilized. Construction complete. ESC permit conditions satisfied.
ESC14-00462 General Inspection7/30/20157/30/20157/31/2015 9:02:40 AM PASS
ESC15-00882 Conference7/28/20157/30/20157/30/2015 4:21:28 PMPPASS
check for BMPs...

DI bag now installed. Will preserve existing vegetation along roadway for this current phase.
ESC15-00748 Site Preparation7/30/20157/30/20157/30/2015 3:15:48 PMPPASS
Silt fence installed to protect neighboring homes. Small lot with old house demolished. Work was approved to start, keeping clean at time of inspection. Permit sign posted. Approved.
ESC15-00748 Site Preparation7/30/20157/30/20157/30/2015 11:40:32 AMACANC
rescheduled for afternoon. Verbal confirmation to start given to excavator RP Luke to start this AM
ESC15-00266 BMP Violation7/29/20157/30/20157/30/2015 11:33:03 AMAPEND
CN issued by Code enforcement to clean up uncontained trash and building debris.

Re-iterated to RP-GC about BLD and ESC permit conditions to contain trash and debris. Site must be cleaned and all materials hauled away, swept up, and remaining waste in trash bins.

Stated to RP that site will be issued SWO on Monday August 3 if site is not cleaned and in compliance.

ESC15-00108 General Inspection7/30/20157/30/20157/30/2015 10:13:52 AM PASS
No exterior disturbance or loose sediment. No further ESC inspections needed.
ESC15-00108 DOC - Permit Finaled7/30/20157/30/20157/30/2015 10:13:19 AMPPASS
ESC15-00107 General Inspection7/30/20157/30/20157/30/2015 9:52:54 AM PASS
ESC13-01279 General Inspection7/30/20157/30/20157/30/2015 9:44:15 AM PASS
No new SFHs being built, no trackout, discharges or other issues. Will start next round of homes in late August or September