ELE19-02224
| Electrical Rough-In | 8/2/2019 | 8/5/2019 | 8/5/2019 2:18:47 PM | P | PASS |
|
|
Inspection of east side duct bank and main electrical room grounding to column. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover duct bank E side building, and bonding of building steel via cad weld.
|
ELE19-02813
| Final | 8/5/2019 | 8/5/2019 | 8/5/2019 1:55:55 PM | P | PASS |
|
|
Please contact Micah Hornback at ###-#### before arrival so that I may meet you on site. Thank you! Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok final. Panel labeled, all stickers present as needed.
|
ELE17-02696
| ELE-Aging Inspection | 8/5/2019 | 8/5/2019 | 8/5/2019 1:30:15 PM | | PASS |
|
|
This is to final out permit. No other work was done.
|
ELE17-02696
| Final | 8/5/2019 | 8/5/2019 | 8/5/2019 1:29:37 PM | P | PASS |
|
|
This is to final out permit. No other work was done.
|
ELE17-02695
| ELE-Aging Inspection | 8/5/2019 | 8/5/2019 | 8/5/2019 1:28:38 PM | | PASS |
|
|
This is to final out permit. No other work was done.
|
ELE17-02695
| Final | 8/5/2019 | 8/5/2019 | 8/5/2019 1:28:11 PM | P | PASS |
|
|
This is to final out permit. No other work was done.
|
ELE19-02290
| Final | 8/5/2019 | 8/5/2019 | 8/5/2019 1:27:38 PM | P | PASS |
|
|
garage code 2468 Phone #: ###-#### Inspection requested via web by Darryn Coburn Ok final
|
ELE19-02545
| Final | 8/2/2019 | 8/5/2019 | 8/5/2019 11:34:22 AM | A | PASS |
|
|
Contact is Todd Sellman Phone #: ###-#### Inspection requested via web by Candy Magly Ok final.
|
ELE19-02882
| Rough-In Permanent Service | 8/2/2019 | 8/5/2019 | 8/5/2019 11:33:56 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk p/s u/g n ok
|
ELE19-02264
| Final | 8/2/2019 | 8/5/2019 | 8/5/2019 10:01:28 AM | A | PASS |
|
|
Man door on side is open. Phone #: ###-#### Inspection requested via web by Dean Gernaat Ok final.
|
ELE19-02796
| Final | 8/1/2019 | 8/5/2019 | 8/5/2019 9:40:57 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Same Electric Ok final. Overhead branch circuit to garage. Gounding system re-established, 1 ground rod. New interior panel labeled.
|
ELE19-02492
| Conference | 8/5/2019 | 8/5/2019 | 8/5/2019 9:14:10 AM | A | PASS |
|
|
Trench is dug with conduit. I''d like to bury it but want the sign off first. Phone #: ###-#### Inspection requested via web by Nick Smith Ok cover trench from house to detached garage. 20"-24" deep.
|
ELE19-02831
| Final | 8/4/2019 | 8/5/2019 | 8/5/2019 9:02:09 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Tyler Ridley Ok final. Panel labeled, intersystem installed.
|