BLD18-04131
| FIRE-Final Inspection | 8/5/2019 | 8/5/2019 | 8/5/2019 3:43:03 PM | P | PASS |
|
|
life safety passed. The contractor, TVR, stated all wiring was explosion proof.
You will need to call Dave ###-#### AND code 0688 for the front door lock box. Phone #: ###-#### Inspection requested via web by Brandon Sorensen
|
FIR19-00525
| INSP-Sprinkler Rough-in | 8/5/2019 | 8/5/2019 | 8/5/2019 2:58:10 PM | P | PASS |
|
|
Rough-in passed for the piping above the hard lids. This piping can be covered.
Phone #: ###-#### Inspection requested via web by Jonathan LaFond
|
NAF18-00133
| INSP-Sprinkler Rough-in/Hydro | 8/5/2019 | 8/5/2019 | 8/5/2019 2:57:26 PM | P | PASS |
|
|
The underground supply line hydro test was witnessed with no pressure loss.
Please call Troy Nelson for inspection time. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
BLD18-00105
| FIRE-Conference | 8/4/2019 | 8/5/2019 | 8/5/2019 12:20:25 PM | A | DONE |
|
|
Andy and I discussed boxing in the exposed piping in the closets, filling with insulation but no insulation on the interior wall side. Also the outer layer of sheet rock on the adjoining wall would be cut out to facilitate the transfer of heat from the interior. We also discussed riser room signage and placement of the interior smokd alarms. call to confirm please! Troy knows what I''m talking about. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD17-03396
| FIRE-Final Inspection | 8/2/2019 | 8/5/2019 | 8/5/2019 11:28:39 AM | A | PASS |
|
|
Life safety passed.
Kurt Phone #: ###-####
|
BLD19-00763
| FIRE-Final Inspection | 8/2/2019 | 8/5/2019 | 8/5/2019 11:18:50 AM | A | CANC |
|
|
I spoke to Sean and he is going to reschedule for tomorrow with the fire alarm inspection. Sean Phone #: ###-####
|
FIR19-00378
| INSP-Final Inspection | 8/5/2019 | 8/5/2019 | 8/5/2019 10:27:18 AM | P | CANC |
|
|
Contact is Dirk. Phone #: ###-#### >> Inspection requested via web by Morgan Ahten Inspection cancelled from web by: Morgan Ahten
|
BLD18-04564
| FIRE-Final Inspection | 8/2/2019 | 8/5/2019 | 8/5/2019 8:08:48 AM | A | PASS |
|
|
Life safety passed. Randy Phone #: ###-####
|
FIR19-00215
| INSP-Final Inspection | 8/2/2019 | 8/5/2019 | 8/5/2019 7:56:17 AM | A | PART |
|
|
The second group (six) of apartments to the north of the central breeze sprinkler work is complete.
Gabe Garduno is the contact for this final inspection. We appreciate your help, thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-03116
| FIRE-Final Inspection | 8/2/2019 | 8/5/2019 | 8/5/2019 7:55:47 AM | A | PART |
|
|
The second group (six) of apartments to the north of the central breeze way life safety is passed. Matt Phone #: ###-####
|
FIR19-00565
| INSP-Final Inspection | 8/2/2019 | 8/5/2019 | 8/2/2019 3:21:04 PM | A | CANC |
|
|
Client requests 6am test time. >> Inspection requested via web by Morgan Ahten Inspection cancelled from web by: Morgan Ahten
|