Inspections for the day of: Friday, September 1, 2017.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-02899 FIRE-Final Inspection8/31/20179/1/20179/1/2017 3:08:18 PMACANC
Herb Phone #: ###-####
FIR16-00738 INSP-Final Inspection8/31/20179/1/20179/1/2017 3:01:32 PMAFAIL
The interconnection with the fire alarm panel needs to be retested due to wrong signals from tamper and pressure switches. Also need the forward flush test for 13psi out of the 2 1/2" drain. Need test papers as well

Adam Phone #: ###-####
FIR14-00701 INSP-Final Inspection9/1/20179/1/20179/1/2017 2:45:09 PMPCANC
John Phone #: ###-####
BLD17-01354 FIRE-Final Inspection8/31/20179/1/20179/1/2017 2:08:09 PMAFAIL
Life safety will be ok to pass when the project related fire alarm pemit has been finaled
FIR16-00284 INSP-Sprinkler Rough-in8/31/20179/1/20179/1/2017 2:07:31 PMAPART
Todays walk through was for the first floor apartments. I noted one painted concealer pendant head and on pendant that is blocked by a surface mounted light.
NAF17-00028 INSP-Final9/1/20179/1/20179/1/2017 11:47:46 AMADONE
Permit finaled per Scott this has been review under the sprinkler design
NAF17-00020 INSP-Final9/1/20179/1/20179/1/2017 11:47:10 AMADONE
permit finaled
FIR17-00261 INSP-Sprinkler Rough-in8/31/20179/1/20179/1/2017 11:16:41 AMAPART
Sprinkler heads outside of new corridor system are ok to cover. One pendant needs to be added in the Storage Room as per plans.
FIR16-00821 INSP-Sprinkler Rough-in8/31/20179/1/20179/1/2017 10:19:06 AMAPART
See the city approved plans for locations clouded where the sprinkler piping rough-in passed. Hat channel can be installed but piping can not be covered until draft stop/compartments can be verified for the CC2 heads.
FIR17-00472 INSP-Final Inspection8/31/20179/1/20179/1/2017 9:42:26 AMAPASS
Permit finaled.
FIR17-00040 INSP-Final Inspection8/31/20179/1/20179/1/2017 9:41:39 AMAFAIL
Todays inspection was just a partial. Installed head end equipment tested ok, manual pull statons tested ok, hood suppression system tested ok. The sprinkler system interconnections have problems as the tamper switches and pressure switches report as a/c power loss. All notification devices tested ok and are sync'd. Need to re-verify the fire sprinkler interconnects, duct detectors, fire door release, security door release, smoke detectors and heat detectors. I verified off site monitoring for the devices tested. Address was ok. Will need as-builts showing the minimal changes.