BLD13-01395
| FIRE-Final Inspection | 9/12/2013 | 9/12/2013 | 9/12/2013 3:38:24 PM | P | PASS |
|
|
life safety passed
|
FIR13-00359
| INSP-Sprinkler Rough-in | 9/12/2013 | 9/12/2013 | 9/12/2013 2:59:31 PM | P | PASS |
|
|
The pipe routing now matches the plan modifications. Still need a tenting inspection on the third floor. Overspaced pendants on the first and second floors have been corrected.
|
FIR13-00359
| INSP-Sprinkler Rough-in/Hydro | 9/12/2013 | 9/12/2013 | 9/12/2013 2:53:45 PM | P | PASS |
|
|
Overhead hydro passed for all floors.
|
FIR13-00344
| INSP-Supply line flush | 9/11/2013 | 9/12/2013 | 9/12/2013 2:49:56 PM | A | FAIL |
|
|
United water has not turned on the water supply yet
|
BLD13-02422
| FIRE-Final Inspection | 9/11/2013 | 9/12/2013 | 9/12/2013 1:37:53 PM | P | PASS |
|
|
Life safety passed.
|
FIR13-00344
| INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/12/2013 | 9/12/2013 12:29:40 PM | A | CANC |
|
|
The underground hydro passed
|
BLD13-01834
| FIRE-Final Inspection | 9/11/2013 | 9/12/2013 | 9/12/2013 10:30:26 AM | P | FAIL |
|
|
ron is going to reschedule for tomorrow since there are no approved plans on site.
|