Inspections for the day of: Friday, September 21, 2018.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-03085 BLD-Footing9/21/20189/21/20189/21/2018 4:09:59 PMPPASS
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell wip set backs ok
BLD18-01790 BLD-Wall Bracing9/21/20189/21/20189/21/2018 4:09:31 PMPPASS
Shear // Omar Phone #: ###-####
BLD17-02477 BLD-Wall cover9/21/20189/21/20189/21/2018 4:09:13 PMPPASS
Cody Phone #: ###-#### rc ok
BLD17-02478 BLD-Final9/21/20189/21/20189/21/2018 4:08:48 PMPPASS
Cody Phone #: ###-####
BLD18-02231 BLD-Framing/Rough-in9/20/20189/21/20189/21/2018 3:20:31 PMPPART
adam Phone #: ###-#### blk and nail hangers to box 1 girder// b1 and b2 missing center bearing point/ ok to insulate// sheer ok
BLD17-00747 BLD-Aging Inspection9/21/20189/21/20189/21/2018 1:19:24 PM PASS
pending fire
BLD18-02329 BLD-Final9/19/20189/21/20189/21/2018 1:18:00 PMADEFR
Final - Call Luke Phone #: ###-#### Inspection requested via web by Brandon Sorensen
BLD18-01641 BLD-Framing/Rough-in9/20/20189/21/20189/21/2018 1:07:29 PMAPASS
unit 201-John Phone #: ###-####
BLD18-01488 BLD-Final9/20/20189/21/20189/21/2018 10:41:00 AMAPASS
Larry Phone #: ###-#### final ok
BLD17-01247 BLD-Final9/20/20189/21/20189/21/2018 10:32:55 AMAPASS
Tim Phone #: ###-#### final ok pending fire// l/c
BLD18-01050 BLD-Foundation9/20/20189/21/20189/21/2018 10:20:22 AMAPASS
Tucker Phone #: ###-#### pend ing center pad at slab
BLD18-02298 BLD-Framing/Rough-in9/20/20189/21/20189/21/2018 10:00:44 AMAPASS
Steve Phone #: ###-####
BLD18-00803 BLD-Footing9/20/20189/21/20189/21/2018 9:34:25 AMAPASS
Kevin Phone #: ###-#### 2 of three ok pending si for all ft/ compaction