Inspections for the day of: Thursday, April 20, 2017.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-03966 BLD-Final4/20/20174/20/20174/20/2017 6:25:53 PMPPASS
Phone #: ###-#### Inspection requested via web by Tracy Lee
BLD17-00735 BLD-Footing4/20/20174/20/20174/20/2017 3:27:03 PMPPASS
Matt Phone #: ###-####
BLD17-00266 BLD-Footing4/20/20174/20/20174/20/2017 2:50:11 PMPPASS
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD17-00448 BLD-Footing4/20/20174/20/20174/20/2017 2:49:55 PMPPASS
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD17-00863 BLD-Framing/Rough-in4/19/20174/20/20174/20/2017 2:49:38 PMPPASS
Please call 30 minutes ahead to allow me to let you in or make sure the owner is home.
Thanks, Phone #: ###-#### Inspection requested via web by Michael Jerome
BLD16-04251 BLD-Framing/Rough-in4/19/20174/20/20174/20/2017 1:55:34 PMPPASS
Please contact Jeremy Schalk project manager at 208.869.9276 before arriving with approximate time of inspection. Jeremy can meet you the gate if needed and give access to plans. Phone #: ###-#### Inspection requested via web by Tim Boesiger
BLD17-00103 BLD-Energy code compliance4/19/20174/20/20174/20/2017 12:15:44 PMAPASS
Insulation // Josh Phone #: ###-####
BLD17-00059 BLD-Foundation4/19/20174/20/20174/20/2017 11:37:19 AMAPASS
Dean Phone #: ###-####
BLD16-04073 BLD-Final4/19/20174/20/20174/20/2017 11:36:56 AMANR
Jeff Phone #: ###-####
Need Approved plans on site. called Jeff......need to fix Gap in floor next to new door.