Inspections for the day of: Friday, January 10, 2020.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE20-00111 Rough-In Permanent Service1/10/20201/10/20201/10/2020 3:11:08 PMPPASS
Phone #: ###-#### Inspection requested via web by Same Electric
Service change only. p/s o/h rec ok
ELE19-04615 Final1/10/20201/10/20201/10/2020 2:28:56 PMPPASS
Phone #: ###-#### Inspection requested via web by Kevin Burke
Corridor clean up good. Thank you.
Final ok
ELE19-04895 Final1/10/20201/10/20201/10/2020 1:39:48 PMPPASS
upstairs bathroom Phone #: ###-#### Inspection requested via web by Ryan Wake Final ok
ELE19-04060 Final1/9/20201/10/20201/10/2020 12:22:10 PMAPASS
Phone #: ###-#### Inspection requested via web by Therrin Robertson Final ok
ELE19-04061 Final1/9/20201/10/20201/10/2020 12:21:44 PMAPASS
Phone #: ###-#### Inspection requested via web by Therrin Robertson Final ok
ELE19-04159 Final1/9/20201/10/20201/10/2020 12:21:23 PMAPASS
Phone #: ###-#### Inspection requested via web by Therrin Robertson Final ok
ELE19-04160 Final1/9/20201/10/20201/10/2020 12:20:58 PMAFAIL
Phone #: ###-#### Inspection requested via web by Therrin Robertson
110.3- Devices shall be wired as per manufacturers instructions. back outdoor receptacles cold. Unable to test.
ELE19-04799 Electrical Rough-In1/9/20201/10/20201/10/2020 11:31:09 AMAPASS
UFER ground at footing north of MSB1 Phone #: ###-#### Inspection requested via web by Jason Parke
Concrete encased electrode, footing sleeves, service entrance conduits up column rough in ok cover.
ELE19-04582 Final1/9/20201/10/20201/10/2020 10:27:51 AMAPASS
Phone #: ###-#### Inspection requested via web by Brad Hoots Final ok
ELE19-02808 Electrical Rough-In1/9/20201/10/20201/10/2020 10:27:21 AMAPASS
walls/ceilings in storefront for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel
110.26- Access shall be provided for all electrical equipment. HVAC unit buried above hardlid.
110.26(A) and (A)(4)(c)- Work space shall be provided for HVAC electrical enclosure and door of enclosure shall open to at least 90 degrees. Copper plumbing lines run in front of door blocking work space and door operation.
Must be corrected for grid inspections.
Tasting reception area outer walls and ceiling not ready.
Back wall of tasting reception area and vestibule walls and ceiling rough in ok cover.
ELE19-03933 Final1/9/20201/10/20201/10/2020 8:53:19 AMAPASS
Install 1 wall signs reading Idaho Power. All Primary power by others Phone #: ###-#### Inspection requested via web by Ken Olsen
Final ok