Inspections for the day of: Wednesday, November 20, 2019.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-03664 Final11/19/201911/20/201911/20/2019 2:23:49 PMPPART
Phone #: ###-#### Inspection requested via web by Tom Jenkins
1 piece of furniture to connect, must verify listing of whip. Signed cord by mistake. TCO ok
ELE19-00602 Electrical Rough-In11/20/201911/20/201911/20/2019 2:05:15 PMPPASS
NW Stair Tower cover. Danny is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen
Level 6 N.W. stair pour rough in ok cover
ELE19-01406 Electrical Rough-In11/20/201911/20/201911/20/2019 1:28:42 PMPPASS
Site underground and pole base Phone #: ###-#### Inspection requested via web by John Mittleider
HVAC underground up tight to building and 2 south pole bases rough in ok cover
ELE19-03488 Electrical Rough-In11/19/201911/20/201911/20/2019 10:46:53 AMAPASS
Please call Luke for R/I inspection of hard lids. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo
Corridor 4 corners, center south corridor, showers, executive bathroom hardlids rough in ok cover.
ELE19-04465 Final11/19/201911/20/201911/20/2019 9:56:39 AMAPASS
Final inspection please. Thank you and have a bless day! Phone #: ###-#### Inspection requested via web by Kyle Lott Final ok
ELE19-04465 Electrical Rough-In11/20/201911/20/201911/20/2019 9:56:26 AMPPASS
Final inspection please. Thank you and have a bless day! Phone #: ###-#### Inspection requested via web by Kyle Lott
New grid rough in ok cover
ELE19-03971 Electrical Rough-In11/19/201911/20/201911/20/2019 9:28:11 AMAPASS
Ceiling inspection above grid ready for cover Phone #: ###-#### Inspection requested via web by Kurt Carlson
Grid rough in ok cover