Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE17-03964 Final6/11/20186/12/20186/12/2018 4:56:50 PMAPASS
Job Foreman: Jay Karel Phone #: ###-#### Inspection requested via web by Laurie Hoelscher final ok
ELE17-01337 Conference6/12/20186/12/20186/12/2018 2:52:36 PMPDONE
TCO meeting items to complete.
Roof HVAC fuses- M3 35,37- 25a max, M3 34,35-55a max, M3 38,40- 25a max, M1 20,22,24- 50a max.
Level 5- 518 bath lighting,
Level 4- 419 bath lighting,
Level 3- 328 not ready, check misc receptacles at coffee bars for spark rings. 325 coffee bar not done.
Level 2- 212, 214, 218, 222, 224, 228 not ready. 217 switched power.
Level 1- Kitchen area incomplete, not tested, lobby area misc open wiring coffee bar, bar area not done, pool area and equipment not done, east HVAC not complete, west stair lighting not done, guest rooms not done, electrical room open boxes, gutters, labels incomplete. Lockout HVAC units in all rooms due to receptacle located behind cover screwed in place. Front landscape not complete, open wiring in misc conduits. Check elevator car lighting over current devices are 15 amp. Meeting room and corridor not tested. Confirm EPD devices for heat tape level 2 roof.
ELE18-01333 Permanent Service6/11/20186/12/20186/12/2018 1:59:24 PMPPASS
Tony is contact. 208.447.7612 Phone #: ###-#### Inspection requested via web by Clint Tate
Check 2" bushing in meter base, original one cut. discussed fireplace changing to TV wall and bed closet removed for TV wall. Bathroom remodelled told shall have dedicated 20 amp receptacle circuit.
p/s u/g rec ok
ELE18-02196 Conference6/12/20186/12/20186/12/2018 1:40:54 PMPDONE
call when on way /// Thomas Phone #: ###-####
Discussed code requirements for a bathroom being added. Wiring done with receptacle fed off bedroom. informed of dedicated 20 amp bathroom receptacle circuit, with tamper resistant, GFCI protection required. Will call for a rough in when ready.
ELE18-00727 Electrical Rough-In6/11/20186/12/20186/12/2018 11:14:07 AMAPASS
Pole bases Phone #: ###-#### Inspection requested via web by Tom Jenkins
Pole bases rough in ok cover
ELE18-01935 Electrical Rough-In6/12/20186/12/20186/12/2018 11:13:18 AMAPASS
Ground work N.E.corner of building Call Craig Phone #: ###-#### Inspection requested via web by Tom Betty
Underground east side to grid line 4 rough in ok cover
ELE18-01573 Electrical Rough-In6/12/20186/12/20186/12/2018 9:42:44 AMAPASS
Ceiling cover. Von is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen
Grid rough in ok cover
ELE18-01457 Electrical Rough-In6/12/20186/12/20186/12/2018 9:34:02 AMAPASS
Call Brad(###-####) for access Phone #: ###-#### Inspection requested via web by Brad Girard
Contractor to pull seperate permit and attach to BLD for suite 670 corridor and vanilla space.
Grid rough in ok cover
ELE18-02175 Temporary Service6/11/20186/12/20186/12/2018 8:55:09 AMAPASS
Phone #: ###-#### Inspection requested via web by Alan Lusk
t/s o/h n ok
ELE18-01289 Final6/11/20186/12/20186/12/2018 8:39:07 AMAPASS
Garage 0243 Phone #: ###-#### Inspection requested via web by Heath Thomas Final ok
ELE14-00475 Conference6/4/20186/12/20186/11/2018 2:49:29 PMACANC
Check for progress on permit for HVAC units on roof east end. Minisplit units. Wrong permit created