ELE19-01406
| Electrical Rough-In | 6/19/2019 | 6/19/2019 | 6/19/2019 3:31:45 PM | P | PASS |
|
|
Level 1 A1 hard lid ceilings and level 1 area B laundry and shipping fire lids and top out. Phone #: ###-#### Inspection requested via web by Tom Betty Added toy room top out added and other areas noted rough in ok cover.
|
ELE19-00436
| Electrical Rough-In | 6/19/2019 | 6/19/2019 | 6/19/2019 2:15:34 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mike McCarrel Guard shack rough in ok cover
|
ELE19-01538
| Rough-In Permanent Service | 6/18/2019 | 6/19/2019 | 6/19/2019 11:27:21 AM | A | PASS |
|
|
Mucho Phone #: ###-#### Rough in ok cover p/s u/g n ok
|
ELE19-02263
| Electrical Rough-In | 6/18/2019 | 6/19/2019 | 6/19/2019 10:43:31 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt Pantry will have plug mold under cabinets. Called and informed ceiling work looked unfinished but all is with remodel cans. Kitchen and pantry rough in ok cover
|
ELE19-02175
| Temporary Service | 6/18/2019 | 6/19/2019 | 6/19/2019 9:55:43 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Dan Cox t/s u/g n ok
|
ELE19-00881
| Permanent Service | 6/18/2019 | 6/19/2019 | 6/19/2019 9:13:16 AM | A | PASS |
|
|
Please call when you are on your way to the site. Phone #: ###-#### Inspection requested via web by Spencer McLean Final ok
|