ELE20-02312
| Electrical Rough-In | 7/10/2020 | 7/10/2020 | 7/10/2020 2:58:06 PM | P | PASS |
|
|
Basement west wall has conduits with wiring out of conduit. All must be removed or terminate in a box as per 300.15. 6 circuits provided for show window receptacles Main level only rough in ok cover
|
ELE20-02226
| Rough-In Permanent Service | 7/10/2020 | 7/10/2020 | 7/10/2020 2:31:46 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk Attic HVAC trimmed at rough in. Rough in ok cover p/s u/g n ok
|
ELE20-02364
| Final | 7/9/2020 | 7/10/2020 | 7/10/2020 12:31:47 PM | A | NH |
|
|
Patrick Rohm is the electrician to contact with questions. Phone #: ###-#### Inspection requested via web by A.M.E. Office No answer at door, contactor unable to reach owner for access. Will recall.
|
ELE19-04918
| Final | 7/9/2020 | 7/10/2020 | 7/10/2020 11:33:09 AM | A | PART |
|
|
South tower 12 units Phone #: ###-#### Inspection requested via web by Todd Hall 101, 102 DW not hooked up, House circuits not complete. Rest of units only south tower TCO ok.
|
ELE20-00912
| Electrical Rough-In | 7/9/2020 | 7/10/2020 | 7/10/2020 10:23:36 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Barbara Szurgot Master bath floor heat rough in ok cover.
|
ELE19-03829
| Electrical Rough-In | 7/9/2020 | 7/10/2020 | 7/10/2020 10:06:00 AM | A | PASS |
|
|
Wall rough-in inspection for the 5th floor. Contact Shawn Evins Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 5 core walls as noted on contractor print rough in ok cover.
|
ELE20-02363
| Electrical Rough-In | 7/9/2020 | 7/10/2020 | 7/10/2020 9:42:24 AM | A | PASS |
|
|
Cover inspection for new framing in tenant space Phone #: ###-#### Inspection requested via web by Steve Craig City approved set of prints on site confirmed. Walls and platforms rough in ok cover.
|