Inspections for the day of: Monday, August 5, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-01219 Final7/31/20198/5/20198/5/2019 3:08:08 PMAPASS
Phone #: ###-#### Inspection requested via web by Steve VanWinkle Final ok
ELE19-01219 Electrical Rough-In8/5/20198/5/20198/5/2019 2:55:42 PMPPASS
Phone #: ###-#### Inspection requested via web by Steve VanWinkle
Listing confirmed. Rough in ok
ELE19-02744 Permanent Service8/5/20198/5/20198/5/2019 2:48:40 PMPPASS
Changing service from overhead to underground for addition to be built. Phone #: ###-#### Inspection requested via web by Kendra Lanham p/s u/g rec ok
ELE19-01800 Final8/2/20198/5/20198/5/2019 2:12:02 PMPFAIL
Final inspection for Street Cell on SE corner of 5th and Jefferson. Gate code is 2914. Contact Jason for questions or directions at ###-####. Phone #: ###-#### Inspection requested via web by Sherry Allen
Gate code did not work. Unable to access disconnecting means. Recall when accessible.
As per Warren Wing with State of Idaho, Trac Utilities only able to installed underground to ground box and electrical contractor must install underground to base of pole and have inspected.
ELE19-00602 Electrical Rough-In8/5/20198/5/20198/5/2019 2:00:06 PMPPASS
PT deck pour from level 2 to 3 rough in ok cover
ELE19-01406 Electrical Rough-In8/5/20198/5/20198/5/2019 1:55:19 PMPPASS
Level 2 area B unit ceilings and walls. Phone #: ###-#### Inspection requested via web by Tom Betty
Area noted and level 1 alcove ceiling rough in ok cover
ELE19-00602 Electrical Rough-In8/2/20198/5/20198/5/2019 1:16:56 PMPNH
Danny PT deck concrete pour at front street garage. Phone #: ###-#### Inspection requested via web by Sean DeLacy
Contact provided is on bereavement leave due to the death of his daughter. Undable ot locate others on site. Provide correct contact number so I do ot have to bother this person again.
ELE19-02063 Conference8/1/20198/5/20198/5/2019 12:47:28 PMAPASS
Please call adam at the number listed for entry into plant Phone #: ###-#### Inspection requested via web by Tye Thomas
Discussed if an equipment grounding conductor will be required from new service disconnect to existing office building for reconnecting power.
250.32 (B)(1)ex 1-2. Equipment grounding conductors not required for existing building that were compliant with previous revisions of this code provided it complies with-
1-No original equipment grounding conductor installed.
2-No other metallic connection between service and remote building.
3- Ground fault protection for equipment has not been installed on suppy side of the feeders.
And grounded conductor is of sufficient size required be 220.61 and 250.122.
Also discussed if seal offs would be required for 2" conduits on skid to as control panel board. Return to engineer to verify this area of classification and correct if needed.
ELE19-01022 Final8/2/20198/5/20198/5/2019 9:24:02 AMAPASS
code 0813 Phone #: ###-#### Inspection requested via web by cal crosby Final ok
ELE19-02828 Electrical Rough-In8/1/20198/5/20198/5/2019 8:29:00 AMANR
We need a uffer inspection for this project. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins
Contractor still waiting for rebar to be installed in footings, asked to reschedule.