Inspections for the day of: Friday, November 16, 2018.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJames Ady
TitleELE-INSPECTOR
Phone #914-4683
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE18-01391 Electrical Rough-In11/15/201811/16/201811/16/2018 2:10:10 PMPPASS
Contact Scott Grisbaum for level 3 area C wall cover inspection. Phone #: ###-#### Inspection requested via web by Tom Betty level 3 area C walls only as marked on print ok to cover
ELE18-04429 Final11/16/201811/16/201811/16/2018 1:04:00 PMPNR
Mucho Phone #: ###-####
ELE18-03789 Final11/14/201811/16/201811/16/2018 1:03:28 PMPPASS
Ready for final inspection Phone #: ###-#### Inspection requested via web by Paul Stewart final ok
ELE18-04429 Electrical Rough-In11/16/201811/16/201811/16/2018 12:35:48 PMPPASS
Mucho Phone #: ###-#### Whole house remodel. Rough in ok
ELE18-04429 Final11/16/201811/16/201811/16/2018 12:35:39 PMPNR
Mucho Phone #: ###-####
ELE18-02156 Electrical Rough-In11/15/201811/16/201811/16/2018 11:17:05 AMAPASS
Electrical rough in for the third phase Phone #: ###-#### Inspection requested via web by Ron Zimmerman Phase 3 rough in ok
ELE18-02207 Final11/15/201811/16/201811/16/2018 9:46:49 AMAPASS
Inspector please call Dan ###-#### before arriving and he will meet you there to let you in. Thank you Phone #: ###-#### Inspection requested via web by Eric Schroeder Final ok
ELE18-04239 Final11/15/201811/16/201811/16/2018 9:25:40 AMAPASS
Phone #: ###-#### Inspection requested via web by BRS Permitting final ok
ELE18-04083 Final11/15/201811/16/201811/16/2018 8:55:22 AMAPASS
Final inspection on light poles at Bldg. 80. Phone #: ###-#### Inspection requested via web by Steve Moss Light poles only Final ok