ELE19-04856
| Electrical Rough-In | 5/19/2020 | 5/19/2020 | 5/19/2020 2:15:50 PM | P | PASS |
|
|
Rough-in Building #5. Thank you Phone #: ###-#### Inspection requested via web by Stuart Welton rough in ok to cover
|
ELE20-01681
| Permanent Service | 5/19/2020 | 5/19/2020 | 5/19/2020 1:32:39 PM | P | PASS |
|
|
Service had to be upgraded to 200 amp. I cannot contact anyone to adjust the permit. Please not this is a service inspection. Will be ready at about 2 pm Phone #: ###-#### Inspection requested via web by Sean Patton p/s u/g rec ok
|
ELE19-04505
| Electrical Rough-In | 5/19/2020 | 5/19/2020 | 5/19/2020 1:14:09 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud 4 exterior soffits only ok to cover
|
ELE18-01261
| Final | 5/18/2020 | 5/19/2020 | 5/19/2020 12:35:13 PM | P | PASS |
|
|
Swimming pool electrical final Phone #: ###-#### Inspection requested via web by Lars Johnson pool only final ok
|
ELE20-01708
| Rough-In Permanent Service | 5/19/2020 | 5/19/2020 | 5/19/2020 11:53:14 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson rough in ok p/s u/g n ok
|
ELE20-01707
| Rough-In Permanent Service | 5/19/2020 | 5/19/2020 | 5/19/2020 11:52:38 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson rough in ok p/s u/g n ok
|
ELE20-01493
| Final | 5/18/2020 | 5/19/2020 | 5/19/2020 10:15:45 AM | A | PASS |
|
|
Key to back door is on top of electrical panel. Phone #: ###-#### Inspection requested via web by Troy Cobb Service change final ok
|
ELE20-01087
| Electrical Rough-In | 5/18/2020 | 5/19/2020 | 5/19/2020 10:02:53 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mark M ceiling ok to cover
|
ELE20-01701
| Electrical Rough-In | 5/18/2020 | 5/19/2020 | 5/19/2020 9:44:43 AM | A | PASS |
|
|
Solar Rooftop Installation Rough-In Inspection Phone #: ###-#### Inspection requested via web by Bryan Lawley listing only ok 40A QO breaker in panel
|
ELE20-01488
| Electrical Rough-In | 5/18/2020 | 5/19/2020 | 5/19/2020 9:27:01 AM | A | PASS |
|
|
Equipotential bonding grid complete with bond wire going back to equipment pad Phone #: ###-#### Inspection requested via web by Jordan Camie EQ bond ok to cover
|
ELE18-01377
| ELE-Aging Inspection | 5/19/2020 | 5/19/2020 | 5/19/2020 6:43:49 AM | | DONE |
|
|
Permit for conference only
|
ELE18-01377
| Final | 5/19/2020 | 5/19/2020 | 5/19/2020 6:43:26 AM | A | PASS |
|
|
Work completed under seperate permit. This permit created for conference only final ok
|