Inspections for the day of: Tuesday, June 4, 2019.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJames Ady
TitleELE-INSPECTOR
Phone #914-4683
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-01080 Final6/4/20196/4/20196/4/2019 2:37:53 PMPPASS
Garage code 1957e Phone #: ###-#### Inspection requested via web by Alan Lusk final ok
ELE19-02033 Temporary Service6/4/20196/4/20196/4/2019 2:24:55 PMPPASS
NEW TEMP POLE---OTHER ON SITE NOT WORKING PROPERLY Phone #: ###-#### Inspection requested via web by Bob Glenn t/s u/g n ok
ELE18-00951 Final5/31/20196/4/20196/4/2019 2:24:07 PMPNR
Alan Phone #: ###-#### not ready
ELE19-01914 Final6/3/20196/4/20196/4/2019 1:06:49 PMPFAIL
Install complete per approved plans; the stamped and approved plans are on site;
For any questions about the work done for this project, call Jed at ###-####; For any questions about the plans or design, call Ryan at ###-####;

The job site is an open site, still under construction, and all our work is exposed. There is a mezzanine inside with a service ladder so you can see our raceways inside as well.

thanks guys
Phone #: ###-#### Inspection requested via web by Ryan King 690.47. PV equipment shall be connected to grounding electrode system.(CT can is not bonded. Connect to red iron or ufer) 250.58. Where supplied by a seperate service. The same grounding electrode system shall be used. 250.24 The grounding electrode conductor shall terminate at an accesible point on the load side of service conductors and on the same bus or terminal as the grounded conductor. (remove grounding conductor from meter base to Fused Disc., Remove Jumper from CT can to Breaker panel. Install Grounding electrode conductor from Fused disc. to existing grounding electrod system. Leave Bonding bushing installed on EMT from meter to Fused disc.)
ELE19-01677 Rough-In Permanent Service6/3/20196/4/20196/4/2019 11:50:54 AMAPASS
Phone #: ###-#### Inspection requested via web by Heath Thomas Corrections made rough in ok p/s u/g n ok
ELE19-01744 Electrical Rough-In6/3/20196/4/20196/4/2019 10:38:35 AMAPASS
Rough-in inspection shall apply to dining/office addition. This includes lighting and receptacles on a new circuit. Thank you very much! Phone #: ###-#### Inspection requested via web by Dan Hilke Areas were givin ok to cover 5/29. Wires were fished in. Nothing new to inspect.
ELE19-01667 Conference6/3/20196/4/20196/4/2019 10:33:37 AMADONE
Mark- please call for access Phone #: ###-#### Talked about Mounting service on house and removing Pedistal. Need to re-call conferance when house is framed
ELE19-00848 Electrical Rough-In6/3/20196/4/20196/4/2019 9:35:46 AMAPASS
Underground rough-in Phone #: ###-#### Inspection requested via web by Stuart Welton Building 8A underground ok to cover
ELE19-00847 Electrical Rough-In6/3/20196/4/20196/4/2019 9:35:15 AMAPASS
Underground rough-in Phone #: ###-#### Inspection requested via web by Stuart Welton Building 7 underground ok to cover
ELE19-00849 Electrical Rough-In6/3/20196/4/20196/4/2019 9:34:29 AMAPASS
Underground rough-in Phone #: ###-#### Inspection requested via web by Stuart Welton Building 8B underground from Main service to panel ok to cover
ELE19-01227 Permanent Service6/3/20196/4/20196/4/2019 9:33:28 AMACANC
Phone #: ###-#### Inspection requested via web by Tyler Bowen
ELE19-01687 Electrical Rough-In6/3/20196/4/20196/4/2019 9:02:40 AMAPASS
Not sure if you need to inspect the public works street lights before we pour but i have called them for inspection tomorrow. If you need to see them before concrete also please do so. Thanks Phone #: ###-#### Inspection requested via web by Tyler Bowen This is a Public works project. Did look at underground. OK to cover
ELE19-01227 Electrical Rough-In6/4/20196/4/20196/4/2019 8:56:00 AMPPASS
Phone #: ###-#### Inspection requested via web by Tyler Bowen Checked Grounding/Bonding of tranfsormers. Ok to energize
ELE18-03913 Final5/30/20196/4/20196/4/2019 8:55:03 AMAPASS
Phone #: ###-#### Inspection requested via web by Eric Landberg Final ok