ELE19-01975
| Electrical Rough-In | 7/15/2019 | 7/15/2019 | 7/15/2019 2:42:42 PM | P | PASS |
|
|
EQ bonding plane wiring and connections Phone #: ###-#### Inspection requested via web by Lars Johnson EQ bond and waterfall UG only ok to cover
|
ELE19-02612
| Final | 7/15/2019 | 7/15/2019 | 7/15/2019 2:08:13 PM | P | PASS |
|
|
Replace mast wire and weather head.- Idaho power will need to reconnect Phone #: ###-#### Inspection requested via web by Kendra Lanham final ok
|
ELE19-02612
| Permanent Service | 7/15/2019 | 7/15/2019 | 7/15/2019 2:07:13 PM | P | PASS |
|
|
Replace mast wire and weather head.- Idaho power will need to reconnect Phone #: ###-#### Inspection requested via web by Kendra Lanham p/s o/h rec ok
|
ELE19-02606
| Temporary Service | 7/15/2019 | 7/15/2019 | 7/15/2019 1:41:43 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by kendall bender t/s o/h n ok
|
ELE19-01403
| Electrical Rough-In | 7/15/2019 | 7/15/2019 | 7/15/2019 11:00:13 AM | A | PASS |
|
|
Inspect 3 boxes and associated raceways in concrete wall southeast corner of the Parking Garage. Contact Justin a few minutes ahead of arrival as he is working on anther project a few blocks away. Phone #: ###-#### Inspection requested via web by Tom Betty Area listed. Conduits and boxes in concrete walls ok to cover
|
ELE19-02231
| Electrical Rough-In | 7/11/2019 | 7/15/2019 | 7/15/2019 10:59:25 AM | A | FAIL |
|
|
Rich Phone #: ###-#### Finish make up(Pigtail receps and switches, finish all attic j-boxes) Swap dryer box with listed 2gang box. Move all staples to outside of 1 1/4in from face of stud. Install smoke detectors per code.
|
ELE19-02596
| Electrical Rough-In | 7/12/2019 | 7/15/2019 | 7/15/2019 9:58:36 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by TOM BICANDI Open KO's in junction box next to furnace(Was an old panel with Busing removed. Master bed,Bath closet and laundry room ok to covert
|
ELE19-01994
| Final | 7/12/2019 | 7/15/2019 | 7/15/2019 9:09:41 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher final ok
|
ELE19-02425
| Electrical Rough-In | 7/12/2019 | 7/15/2019 | 7/15/2019 8:54:36 AM | A | PASS |
|
|
cover inspection contact is Deeon Martineau Phone #: ###-#### Inspection requested via web by Scott Campbell Medium voltage undergound and grounding ok to cover
|
ELE19-01400
| Final | 7/13/2019 | 7/15/2019 | 7/15/2019 8:27:54 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Thomas wilson Final ok
|