Inspections for the day of: Friday, August 5, 2016.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJames Ady
TitleELE-INSPECTOR
Phone #914-4683
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-01666 ELE-Aging Inspection8/5/20168/5/20168/9/2016 3:24:16 PM DONE
Still working on project
ELE16-02150 Final8/5/20168/5/20168/5/2016 2:07:23 PMPPART
CONTACT: PAUL WHEELER, LATE AFTERNOON PLEASE Phone #: ###-#### Inspection requested via web by Deb Gooden Partial Final ok
ELE16-01416 Electrical Rough-In8/5/20168/5/20168/5/2016 1:31:32 PMPPASS
Pool bond grid on spa and pool Phone #: ###-#### Inspection requested via web by Emmet Bushman Equipotential bond ok
ELE16-01013 Final8/4/20168/5/20168/5/2016 1:19:52 PMPPASS
Call Russ the homeowner 1/2 prior to inspection. ###-####
Thanks Mike (I will be out of town working) Phone #: ###-#### Inspection requested via web by MIKE HAGERTY Final ok
ELE16-01363 Final8/5/20168/5/20168/5/2016 12:52:22 PMPFAIL
please call ###-#### with questions Phone #: ###-#### Inspection requested via web by Brian Hughes 210.63 Air conditioniong equipment recep.
422.31 Appliance disconnect. Water heater
ELE16-02545 Electrical Rough-In8/5/20168/5/20168/5/2016 12:13:25 PMPFAIL
Jessica// please call before Phone #: ###-####k 210.52 D all bathrooms shall have 1 recep within 3ft of each basin.
314.16 Boxfill. Junction box on ceiling overfilled. 30in box minimum. Also broken
ELE16-02549 Rough-In Permanent Service8/5/20168/5/20168/5/2016 11:15:33 AMPPASS
Phone #: ###-#### Inspection requested via web by ron spen cer Rough in ok to cover p/s o/h n ok
ELE16-02527 Final8/4/20168/5/20168/5/2016 10:43:41 AMAPASS
Carl Phone #: ###-#### Platform made. final ok
ELE16-01158 Final8/5/20168/5/20168/5/2016 10:04:43 AMAPASS
Mini split system wiring complete in upper bonus room ready for overall project final. Thank You Inspection requested via web by Robert Schroder Final ok
ELE16-01937 Electrical Rough-In8/4/20168/5/20168/5/2016 9:40:50 AMAPASS
Requesting inspection for ok to cover floor heat in Master bath.
Please call ###-#### half hour prior to arrival.
Thank you Phone #: ###-#### Inspection requested via web by John Edwards Master floor heat ok to cover
ELE16-02533 Temporary Service8/3/20168/5/20168/5/2016 9:29:50 AMAPASS
Temp Power Phone #: ###-#### Inspection requested via web by Zane Robertson t/s u/g n ok
ELE16-02531 Temporary Service8/3/20168/5/20168/5/2016 9:29:20 AMAPASS
Temp Power Phone #: ###-#### Inspection requested via web by Zane Robertson t/s u/g n ok
ELE16-02352 Rough-In Permanent Service8/4/20168/5/20168/5/2016 9:20:07 AMAPASS
This will be for underground cover please. Contact if Justin Metcalf ###-####. Please call him if you have any questions. Thank you and have a super day! Phone #: ###-#### Inspection requested via web by Laura Longshaw Underground ok to cover to greenhouse and gate. p/s u/g n ok