Inspections for the day of: Wednesday, May 8, 2019.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDaryl Spivey
TitlePLM-INSPECTOR
Phone #794-9485
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM19-00786 Plumbing Rough-in5/7/20195/8/20195/9/2019 8:11:49 AMPPART
Job # 52539 Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
waste faled..water ok...........ds
PLM19-00784 Plumbing Rough-in5/7/20195/8/20195/9/2019 8:11:48 AMPPASS
Job # 52537 Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
PLM19-01855 Final5/7/20195/8/20195/8/2019 3:46:45 PMPFAIL
Phone #: ###-#### Inspection requested via web by Cameron Neddo
need expansion tank on w/h, and air gaps on indirect wastes to floor sink and pump on icemaker..........ds
PLM19-01861 Other5/8/20195/8/20195/8/2019 3:41:11 PMPPART
Tapped House water service for RP connection for landscaper/sprinkler system. Main and drain.
Please call 208 989 2239 if have questions Joshua Inspection requested via web by Joshua Mcwhinney
test RP..........
PLM19-01090 Final5/6/20195/8/20195/8/2019 3:22:38 PMPPASS
Call ahead to meet // Stephen is your contact on site, contractor for access.. Thanks. Scott. Phone #: ###-#### Inspection requested via web by Scott Sparrell
PLM19-01742 Plumbing Rough-in5/7/20195/8/20195/8/2019 3:18:34 PMPPASS
Please contact Luke Karel if you have any questions. ###-#### Phone #: ###-#### Inspection requested via web by Luke Karel
PLM19-01587 Water and/or Sewer5/8/20195/8/20195/8/2019 3:04:57 PMPPASS
Phone #: ###-#### Inspection requested via web by Chris Field
PLM19-01587 DOC - Permit Finaled5/8/20195/8/20195/8/2019 3:01:38 PMPPASS
PLM18-04409 Final5/7/20195/8/20195/8/2019 1:58:40 PMPPASS
Brad ###-#### Phone #: ###-#### Inspection requested via web by Brent Lacy
PLM19-00242 Final5/8/20195/8/20195/8/2019 1:37:31 PMPPASS
Jason Phone #: ###-####
PLM19-01642 Water and/or Sewer5/6/20195/8/20195/8/2019 1:21:16 PMPPASS
Backflow certified. Ready for final on sprinkler system. Phone #: ###-#### Inspection requested via web by Al Baun
PLM19-01642 Sprinkler (Final)5/8/20195/8/20195/8/2019 1:20:57 PMPPASS
Backflow certified. Ready for final on sprinkler system. Phone #: ###-#### Inspection requested via web by Al Baun
PLM19-01836 Groundwork5/8/20195/8/20195/8/2019 1:13:48 PMPPART
if questions call Steve @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
W/V on bathroom group ok...............ds
PLM18-00340 PLM-Aging Inspection5/8/20195/8/20195/8/2019 11:53:34 AM PASS
will sched.......ds
PLM19-01826 Water Heater Final5/7/20195/8/20195/8/2019 11:19:06 AMAPASS
Please inspect after 9:30 and call Norm Noonan prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette
PLM19-01831 Groundwork5/6/20195/8/20195/8/2019 11:04:24 AMAPASS
Please call Anthony en route ###-####. Thank you Phone #: ###-#### Inspection requested via web by Ben Davis
PLM18-02443 Other5/8/20195/8/20195/8/2019 10:54:51 AMAPASS
Take a look at potable & non-potable water.
backflows all in place for protection...........1 on service, 1 on pool water and 1 for baboon bubblers...discussed d/f freeze problems..........ds
PLM19-01268 Groundwork5/7/20195/8/20195/8/2019 10:24:06 AMAPART
if questions call Steve @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
partial on grease, flammable and roof drainage............ds
PLM19-01751 Water Heater Final5/3/20195/8/20195/8/2019 9:36:51 AMAPASS
AM INSPECTION PLEASE. CALL ###-#### Phone #: ###-#### Inspection requested via web by Kelli Morgan
PLM19-01769 Plumbing Rough-in5/7/20195/8/20195/8/2019 9:17:42 AMAPASS
Phone #: ###-#### Inspection requested via web by John Treat
PLM19-01760 Sprinkler (Final)5/8/20195/8/20195/8/2019 8:47:05 AMAPASS
PLM19-01587 Water and/or Sewer5/3/20195/8/20195/8/2019 7:51:04 AMACANC
Phone #: ###-#### >> Inspection requested via web by Chris Field Inspection cancelled from web by: Chris Field