Inspections for the day of: Wednesday, December 11, 2019.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBrian Scoles
TitleMEC INSPECTOR
Phone #914-4915
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-02134 Final12/6/201912/11/201912/11/2019 3:44:01 PMPPASS
Please call when on the way. Thank you Phone #: ###-#### Inspection requested via web by Denise Colin- furnace only in attic ok
MEC19-04687 Pressure Test12/11/201912/11/201912/11/2019 2:57:29 PMPPASS
20lb gas pass underground only- ok for backfill
MEC19-05489 Rough-in12/11/201912/11/201912/11/2019 2:50:28 PMPPART
Rough in inspection on duct system - manuals on site - will be testing gas supply line to aud to 60llbs at a later date. Phone #: ###-#### Inspection requested via web by Dave Sorensen- R/I will pass once regulator is installed in attic and inspected- ok to cover walls only at this time- check equipment at final not set on R/I- still need 60lb gas test witnessed when ready- will need duct blast and air balance at final
MEC19-05590 Final12/11/201912/11/201912/11/2019 1:49:26 PMPPASS
homeowner has a medical condition where he has to be in bed until noon
he said he can meet inspector at the house at anytime after 1 pm today

Inspection requested via web by Manuel Canto- furnace only co ok
MEC19-05582 Rough-in12/10/201912/11/201912/11/2019 11:14:28 AMAPASS
call Fred with any questions ###-#### Phone #: ###-#### Inspection requested via web by Nick Drake- bldg 2 lineset in walls and condensate ok- ok to cover- will look at exposed remainder on final
MEC19-02863 Final12/10/201912/11/201912/11/2019 10:33:33 AMAPASS
final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- final ok- card signed
MEC19-02864 Final12/10/201912/11/201912/11/2019 10:33:11 AMAPASS
final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- final ok- card signed
MEC19-05363 Pressure Test12/6/201912/11/201912/11/2019 10:02:51 AMAPASS
Brian approved 10am appointment. Call J;D Heating and Cooling technician Kane Cunningham (###-####) when heading over. Also, please do a final inspection at the same time, Thank you Michele. Phone #: ###-#### Inspection requested via web by Simone White- 5lb flue pass
MEC19-05363 Final12/11/201912/11/201912/11/2019 10:02:35 AMAPASS
Brian approved 10am appointment. Call J;D Heating and Cooling technician Kane Cunningham (###-####) when heading over. Also, please do a final inspection at the same time, Thank you Michele. Phone #: ###-#### Inspection requested via web by Simone White- furnace only co ok- 5lb flue pass
MEC19-05366 Final12/9/201912/11/201912/11/2019 9:16:31 AMAPASS
Call ahead to Samantha @ ###-#### Phone #: ###-#### Inspection requested via web by Nicole Smith- furnace only co ok
MEC19-04643 Final12/10/201912/11/201912/11/2019 8:48:52 AMAPASS
Phone #: ###-#### Inspection requested via web by Oleg Chervak- final ok
MEC18-02914 Mec-Aging Inspection12/11/201912/11/201912/11/2019 7:53:20 AM DONE
WIP-
MEC19-02176 Mec-Aging Inspection12/11/201912/11/201912/11/2019 7:52:30 AM DONE
MEC19-02176 Final12/11/201912/11/201912/11/2019 7:52:22 AMAPASS
electrical permit issued and finaled
MEC19-04631 Final12/11/201912/11/201912/11/2019 7:45:57 AMAPASS
furnace a/c coil co locking caps ok
MEC19-05363 Pressure Test12/6/201912/11/201912/6/2019 9:53:57 AMACANC
Please schedule first thing in the morning and call J&D Heating and Cooling technician Kane Cunningham (###-####) 30 minutes prior to appointment. Also, please do a final inspection at the same time, Thank you. Phone #: ###-#### >> Inspection requested via web by Simone White Inspection cancelled from web by: Simone White