MEC18-02982
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 4:07:18 PM | P | PASS |
|
|
Inspection requested via web by Marisa Hone- furnace a.c coil co ok
|
MEC19-00752
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 3:14:24 PM | P | PASS |
|
|
INSTALLER DAVID ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- furnace a/c coil co ok
|
MEC19-00730
| Final | 2/19/2019 | 2/21/2019 | 2/21/2019 2:27:04 PM | P | PASS |
|
|
Client will be available between 10 AM and 3PM. Thank you Phone #: ###-#### Inspection requested via web by Andrea Grigsby- furnace only co ok
|
MEC19-00596
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 1:34:07 PM | P | PASS |
|
|
after 100pm- ###-####- Britt- furnace coil only co ok
|
MEC19-00746
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 11:28:07 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Floyd Floyd Peek- furnace only co ok
|
MEC19-00746
| Pressure Test | 2/20/2019 | 2/21/2019 | 2/21/2019 11:26:04 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Floyd Floyd Peek- 5lb flue test pass
|
MEC18-05917
| Rough-in | 2/20/2019 | 2/21/2019 | 2/21/2019 11:14:06 AM | A | PART |
|
|
sealing and fire damper framing Phone #: ###-#### Inspection requested via web by Nicholas Paige- area 2 C/D need some framing on 3 dampers addressed- rest are good- recall in when seal and framing completed
|
MEC19-00173
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 10:16:05 AM | A | PASS |
|
|
Installed range hood, Ran gas from cabinet stub out to gas cook top. Hooked range hood duct up. Sealed joints. If there are any questions please call Gary. Thank you. Phone #: ###-#### Inspection requested via web by Gary Duncan- final ok
|
MEC18-03194
| Rough-in | 2/20/2019 | 2/21/2019 | 2/21/2019 9:38:35 AM | A | PASS |
|
|
Rough-in on first-floor eastside. Please call Patrick prior to arrival at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Maira Napoles- R/I ok 1st floor- pipe insulation needs to be plenum rated
|
MEC18-03194
| Pressure Test | 2/21/2019 | 2/21/2019 | 2/21/2019 9:37:22 AM | A | PASS |
|
|
Rough-in on first-floor eastside. Please call Patrick prior to arrival at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Maira Napoles- 1st floor only 100# test on hydronics pass- ok for insulation
|
MEC18-04954
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 9:09:02 AM | A | FAIL |
|
|
Inspection requested via web by Marisa Hone- needs to schedule a flue test to be witnessed- single wall flue from water heater needs 6" clearance to pvc flue on furnace- need to pull water heater permit for new water heater thats installed- furnace a/c coil co ok
|
MEC19-00466
| Final | 2/20/2019 | 2/21/2019 | 2/21/2019 8:32:22 AM | A | PASS |
|
|
IF THERE IS ANY ISSUES PLEASE LET US KNOW. MY NAME IS STEVE WITH DIAMOND HEATING. Phone #: ###-#### Inspection requested via web by Rick Montgomery- final ok
|