MEC19-02225
| Final | 5/30/2019 | 6/3/2019 | 6/3/2019 3:55:35 PM | P | PASS |
|
|
Chuck ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks
|
MEC19-02225
| Pressure Test | 5/30/2019 | 6/3/2019 | 6/3/2019 3:55:04 PM | P | PASS |
|
|
Chuck ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks- 20lb gas pass co ok
|
MEC19-01139
| Final | 5/31/2019 | 6/3/2019 | 6/3/2019 3:22:10 PM | P | NR |
|
|
PM inspection - final - call scott Phone #: ###-#### Inspection requested via web by Brandon Sorensen- still need to remove seperation wall and install grid to have registers installed in- talked with GC onsite-
|
MEC19-02103
| Final | 5/31/2019 | 6/3/2019 | 6/3/2019 3:04:35 PM | P | CANC |
|
|
PLEASE CALL HOMEOWNER JENNIFER WHEN 30 MINS IN ROUTE Phone #: ###-#### Inspection requested via web by Rick Montgomery- no adult at home to do inspection- i rescheduled this for next monday in am
|
MEC19-02265
| Final | 5/31/2019 | 6/3/2019 | 6/3/2019 2:49:32 PM | P | PASS |
|
|
Please call Dave on your way - ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks- furnace only co ok
|
MEC19-02237
| Final | 5/30/2019 | 6/3/2019 | 6/3/2019 2:18:16 PM | P | PASS |
|
|
INSTALLER GERRY ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- furnace a/c coil co ok
|
MEC19-00845
| Final | 6/3/2019 | 6/3/2019 | 6/3/2019 1:54:20 PM | P | PART |
|
|
Dan ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks- 4 units upstairs need duct blast test- Daniel has call into Chad S about duct blast hes out sick today- will final out when issues resolved
|
MEC18-05338
| Final | 5/31/2019 | 6/3/2019 | 6/3/2019 1:12:22 PM | P | PART |
|
|
if questions call Mike C. @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- gas piping after shutoff valve to unit heater 6 needs extended down has conflict with fkue vent, flue vent needs grade to outside and gas line is pushing it up- need to seal weather tight exterior penetration at meter location- went over onsite with installer- will final this permit out when other Mech contractor inspection is completed- Rest is good
|
MEC19-01996
| Final | 5/31/2019 | 6/3/2019 | 6/3/2019 12:36:05 PM | P | PASS |
|
|
Please call Dave to ensure install is complete. Thank you! ###-#### Phone #: ###-#### Inspection requested via web by Rick Borg- furnace a/c coil co ok
|
MEC18-02254
| Final | 6/3/2019 | 6/3/2019 | 6/3/2019 12:01:10 PM | P | PART |
|
|
if questions call Ryan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann- all gas piping in seating area ok- who did gas piping to all equipment in kitchen area never been inspected ?
|
MEC18-05917
| Rough-in | 6/3/2019 | 6/3/2019 | 6/3/2019 11:31:45 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- area E to grid line 16 registers flex and labeling on fire damper doors ok- ok for ceiling tiles- still need labeling on grid all areas
|
MEC19-02204
| Final | 6/3/2019 | 6/3/2019 | 6/3/2019 10:41:53 AM | A | PASS |
|
|
final ok
|
MEC19-02204
| Rough-in | 6/3/2019 | 6/3/2019 | 6/3/2019 10:41:17 AM | P | PASS |
|
|
Jason Phone #: ###-####- 3 supplies and 2 return ducts ok- ok to cover
|
MEC18-05852
| Final | 5/31/2019 | 6/3/2019 | 6/3/2019 9:56:17 AM | A | PASS |
|
|
Garage code: 2102 Replaced kitchen hood vent with rigid duct Replaced water heater vent with B vent Phone #: ###-#### Inspection requested via web by Michael Stimpson
|
MEC19-02254
| Rough-in | 5/31/2019 | 6/3/2019 | 6/3/2019 8:27:37 AM | A | PASS |
|
|
cover for common area bathrooms Phone #: ###-#### Inspection requested via web by Brandon Sorensen- 2 supply 2 bath ducts ok- seal, flex and registers ok- ok to cover
|
MEC18-05127
| Mec-Aging Inspection | 6/3/2019 | 6/3/2019 | 6/3/2019 8:05:11 AM | | FAIL |
|
|
needs called in for final inspection if works complete and all noted items on pressure test inspection notes need addressed
|