Inspections for the day of: Monday, January 7, 2019.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE12-00588 ELE-Aging Inspection1/7/20191/7/20191/11/2019 10:48:29 AM DONE
Still appears to be under construction.
ELE18-03107 Final1/4/20191/7/20191/7/2019 2:40:48 PMPPASS
Ken Williams is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok final. Rooftop units have disc, and service recepts present.
ELE18-04509 Electrical Rough-In1/4/20191/7/20191/7/2019 1:38:56 PMPNR
Phone #: ###-#### Inspection requested via web by Rob Maes Nobosy on site. Was at job from 1245-115. Called and left message.
ELE18-04835 Electrical Rough-In1/4/20191/7/20191/7/2019 1:35:45 PMPPASS
Wall cover inspection Phone #: ###-#### Inspection requested via web by Shawn Case Ok cover exam rooms for physical therapy.
ELE17-03951 Electrical Rough-In1/4/20191/7/20191/7/2019 12:32:00 PMAPASS
CONTACT: CLAYTON PENNINGTON... ceiling inspection, corridor area A please Phone #: ###-#### Inspection requested via web by Deb Gooden Ok cover ceilings main hall N entry.
ELE17-03370 Electrical Rough-In1/4/20191/7/20191/7/2019 10:12:41 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Ok cover 4 offices basement area-A, 1st floor ceilings.
ELE19-00081 Electrical Rough-In1/6/20191/7/20191/7/2019 9:54:58 AMAPASS
garage access from alley is easiest. Phone #: ###-#### Inspection requested via web by steve sellers Ok cover garage.
ELE19-00077 Final1/4/20191/7/20191/7/2019 9:19:07 AMAPASS
Phone #: ###-#### Inspection requested via web by Matthew White Ok final. 10-3 and 30a brkr used.
ELE19-00065 Final1/4/20191/7/20191/7/2019 8:48:20 AMAPASS
Phone #: ###-#### Inspection requested via web by Ryan Wilson Ok final. Max fuse 35. 30a brkr installed.