ELE19-03845
| Electrical Rough-In | 12/13/2019 | 12/13/2019 | 12/13/2019 1:50:41 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher Ok final. All signs have disc.
|
ELE19-04266
| Electrical Rough-In | 12/13/2019 | 12/13/2019 | 12/13/2019 1:14:18 PM | P | PASS |
|
|
ceiling Inspection, Chad Vanorden is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover conference rm and warehouse ceilings.
|
ELE19-03608
| Final | 12/12/2019 | 12/13/2019 | 12/13/2019 12:44:04 PM | P | PASS |
|
|
Requesting a final on this job, please. The general contractor should be on site . Phone #: ###-#### Inspection requested via web by todd cline Ok final
|
ELE19-03698
| Final | 12/13/2019 | 12/13/2019 | 12/13/2019 12:34:21 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher Ok final.
|
ELE19-04352
| Rough-In Permanent Service | 12/12/2019 | 12/13/2019 | 12/13/2019 11:53:12 AM | P | PASS |
|
|
Inspection requested via web by ERIC CENTERS Ok cover p/s u/g n ok
|
ELE19-00947
| Electrical Rough-In | 12/12/2019 | 12/13/2019 | 12/13/2019 10:52:42 AM | A | PASS |
|
|
Andy Phone #: ###-#### Ok cover 2 classrooms and bathrooms main level, and classroom 2nd floor.
|
ELE19-04511
| Electrical Rough-In | 12/12/2019 | 12/13/2019 | 12/13/2019 9:50:33 AM | A | PASS |
|
|
There will be someone there. If you have any questions please feel free to contact Kaiden ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok cover whole house.
|
ELE19-03470
| Final | 12/12/2019 | 12/13/2019 | 12/13/2019 9:18:51 AM | A | PASS |
|
|
Robert Phone #: ###-#### Ok final. Max fuse of 30 is installed
|