ELE19-03832
| Final | 12/2/2019 | 12/2/2019 | 12/2/2019 2:34:50 PM | P | PASS |
|
|
Home will be unlocked for access. Phone #: ###-#### Inspection requested via web by Paula Gratiot Ok final.
|
ELE17-02381
| Final | 12/2/2019 | 12/2/2019 | 12/2/2019 2:16:19 PM | P | PASS |
|
|
Scott Phone #: ###-#### Ok final. Items addressed were corrected.
|
ELE19-04497
| Electrical Rough-In | 12/2/2019 | 12/2/2019 | 12/2/2019 1:39:03 PM | P | PASS |
|
|
call on the way // Jason Phone #: ###-#### Ok cover house, above garage and garage except need #4 copper to ufer. Now has #6.
|
ELE19-04403
| Electrical Rough-In | 12/2/2019 | 12/2/2019 | 12/2/2019 1:37:47 PM | P | PASS |
|
|
Greg Phone #: ###-#### Ok cover entry of lower area on detached garage, and up bath and kitchen.
|
ELE19-04629
| Permanent Service | 12/2/2019 | 12/2/2019 | 12/2/2019 1:37:02 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Same Electric p/s o/h rec ok
|
ELE19-03191
| Electrical Rough-In | 12/2/2019 | 12/2/2019 | 12/2/2019 11:06:59 AM | P | PASS |
|
|
Aaron Phone #: ###-#### Ok cover garage and above.
|
ELE19-00947
| Electrical Rough-In | 11/29/2019 | 12/2/2019 | 12/2/2019 10:18:52 AM | A | PASS |
|
|
underground // Andy Phone #: ###-#### Ok cover grd work from IDP trans to building on NE corner.
|
ELE19-01846
| ELE-Request for Extension | 11/29/2019 | 12/2/2019 | 12/2/2019 10:01:35 AM | A | DONE |
|
|
Lara Phone #: ###-#### Talked to homeowner. They just moved back into town and are completely moved. They need more time for their final. Extension ok.
|
ELE19-04024
| Final | 12/1/2019 | 12/2/2019 | 12/2/2019 8:51:57 AM | A | CANC |
|
|
It will be open. If you have any questions please feel free to contact Chaz ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Power not swung yet.. Cant do a final.
|