Inspections for the day of: Friday, February 7, 2020.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-03595 Permanent Service2/7/20202/7/20202/7/2020 2:47:45 PMPPASS
2 grd rods, grds/neut seperated in sub. p/s o/h rec ok
ELE20-00245 Conference2/6/20202/7/20202/7/2020 2:10:11 PMPDONE
after 2:00 would be best if possible. Thank you Phone #: ###-#### Inspection requested via web by Ray Anchustegui Discussed outlet layout for mstr bed/bath, and bed in basement. Homeowner competent.
ELE19-04249 Final2/7/20202/7/20202/7/2020 1:54:11 PMPPASS
Phone #: ###-#### Inspection requested via web by Heath Thomas Ok final.
ELE19-04692 Final2/7/20202/7/20202/7/2020 1:31:48 PMPCANC
Phone #: ###-#### Inspection requested via web by Kyle Zibrowski
ELE19-03311 Final2/6/20202/7/20202/7/2020 1:23:19 PMAPASS
Phone #: ###-#### Inspection requested via web by Bonnie Page Ok final.
ELE20-00407 Final2/7/20202/7/20202/7/2020 1:07:07 PMPPASS
Replaced three coolers inside store Phone #: ###-#### Inspection requested via web by Tyler Ridley Ok final.
ELE20-00391 Electrical Rough-In2/7/20202/7/20202/7/2020 12:29:04 PMPPASS
house is vacant will have front door unlocked, call for questions. Phone #: ###-#### Inspection requested via web by steve sellers Ok cover kitchen. Box to right of sink has 14/2 junctioned through, and a dedicated 12/2 for a refer.
ELE19-04427 Final2/7/20202/7/20202/7/2020 12:16:17 PMPPASS
Key is on top of meter base around back. Phone #: ###-#### Inspection requested via web by Cevyn Recla Ok final.
ELE19-03595 Electrical Rough-In2/6/20202/7/20202/7/2020 12:04:53 PMPCANC
Pre-release inspection to allow ID Power to reconnect the power. Phone #: ###-#### Inspection requested via web by BRS Permitting I scheduled a permanent service, no rough in.
ELE19-02224 Electrical Rough-In2/6/20202/7/20202/7/2020 12:03:11 PMAPASS
2nd floor MOB area ''A'' west side wall rough-in and 1st floor MOB area ''A" west side exam rooms wall rough-in. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed
ELE19-04028 Final2/6/20202/7/20202/7/2020 10:56:49 AMAPASS
House is unoccupied. someone will probably be there working. There is a key to back door located on a j-box near the door. Phone #: ###-#### Inspection requested via web by Troy Cobb Ok final.
ELE19-00947 Electrical Rough-In2/6/20202/7/20202/7/2020 10:03:57 AMAPASS
Andy Phone #: ###-#### Ok cover ceilings 4 classrooms 2nd floor, flex room, and vestibule N side.
ELE20-00357 Final2/6/20202/7/20202/7/2020 9:08:24 AMAPASS
Paul ###-#### Rescheduled from 2/6 to verify bench removal. Ok final. Met on site with Paul and verified removal of bench in front of panel on N wall.