ELE19-01775
| Electrical Rough-In | 5/14/2019 | 5/14/2019 | 5/14/2019 4:03:52 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by TRENT Swaim Ok cover majority of ceiling in main area, and misc throughout.
|
ELE19-01327
| Permanent Service | 5/14/2019 | 5/14/2019 | 5/14/2019 1:25:26 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Bryan McLaughlin p/s u/g rec ok
|
ELE18-01605
| Electrical Rough-In | 5/14/2019 | 5/14/2019 | 5/14/2019 12:49:27 PM | P | PASS |
|
|
A Building 4th Floor Corridor and lobby areas Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover areas listed.
|
ELE19-01762
| Permanent Service | 5/13/2019 | 5/14/2019 | 5/14/2019 12:28:16 PM | P | PASS |
|
|
If possible please call ahead would like to meet you there thank you have a good day Phone #: ###-#### Inspection requested via web by TRENT Swaim p/s o/h n ok
|
ELE18-02379
| Final | 5/13/2019 | 5/14/2019 | 5/14/2019 11:53:45 AM | A | NH |
|
|
Any Questions please call Louis at ###-#### Phone #: ###-#### Inspection requested via web by Louis Keller Please coordinate a time for final inspection.
|
ELE15-00884
| ELE-Aging Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 11:33:00 AM | | FAIL |
|
|
Corrections need made on S light pole off state st or will be turned over to Chief Inspector Daryl DeGrange.
|
ELE19-01410
| Electrical Rough-In | 5/13/2019 | 5/14/2019 | 5/14/2019 11:27:03 AM | A | PASS |
|
|
100 % rough in Phone #: ###-#### Inspection requested via web by jamie berg Ok cover remainder of 1st floor, and open basement on S side.
|
ELE19-01777
| Electrical Rough-In | 5/14/2019 | 5/14/2019 | 5/14/2019 11:14:52 AM | P | CANC |
|
|
Please inspect exterior soffit cans for cover. Phone #: ###-#### Inspection requested via web by Robert Schroder No soffit inspection required as it is not a WUI zone.
|
ELE19-00623
| Final | 5/12/2019 | 5/14/2019 | 5/14/2019 10:49:39 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kyle Dillon Ok final.
|
ELE19-01397
| Permanent Service | 5/14/2019 | 5/14/2019 | 5/14/2019 10:01:20 AM | P | PASS |
|
|
Justin Metcalf ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg 2 grd rods. Interior panel grds/neut seperated. p/s o/h n ok
|
ELE18-03864
| Final | 5/13/2019 | 5/14/2019 | 5/14/2019 9:31:30 AM | A | PASS |
|
|
Key under porcelain frog Phone #: ###-#### Inspection requested via web by Zane Robertson Ok final.
|
ELE18-03869
| Final | 5/13/2019 | 5/14/2019 | 5/14/2019 9:15:34 AM | A | PASS |
|
|
I will be there from 8-11 I can walk you through everything if your able to make it around that time thanks. Phone #: ###-#### Inspection requested via web by Trevor Soesbe Ok final. Unable to verify everything as furniture was moved in and occupied. Floor heat in mstr bath was changed. 1st inspection was orange detra matting. According to the electrician, Tom Mitchum from Advanced Design Services wanted to use different tile. So Tom removed existing istall that was already inspected and changed the brand of floor heat. He forgot to intall the thermostat wire. He said he wasnt going to tear the floor out, he was just going to run the thermo under the base board. I told the electrician to cut floor heat homerun to disable the install. He did.
|
ELE19-01751
| Electrical Rough-In | 5/13/2019 | 5/14/2019 | 5/14/2019 9:05:49 AM | A | PASS |
|
|
Garage in back off of alley way. Side door is open. Phone #: ###-#### Inspection requested via web by Jake Cutler Ok cover gargage. All wiring run vertical, no protection needed.
|