Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE20-02337 Permanent Service7/8/20207/10/20207/10/2020 3:35:20 PMPPASS
There will be guys there working. If you have any questions please feel free to contact Andrew ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clayton Morgan p/s u/g n ok
ELE19-03017 Final7/10/20207/10/20207/10/2020 1:01:57 PMAPART
exterior building Phone #: ###-#### Inspection requested via web by Debby Pierce Partial final. Waiting for possible commisioning report. General said there was only 1 for mechanical, is checking for the electrical side.
ELE19-00669 DOC - Permit Expired7/9/20207/10/20207/10/2020 12:33:19 PMACANC
can you expire or final this one? ele19-01262 probably took its place.. thanks,, Tony 415 Moved to 7/13 so I can contact contractor, I had a few questions on panel
ELE20-01113 Final7/9/20207/10/20207/10/2020 12:25:50 PMPPASS
Ground works final inspection
We are powering up the sub feeder
Main panel to sub panel
Anything after Sub Panel Homeowner is responsible Phone #: ###-#### Inspection requested via web by Eric Schroeder Ok final. Contractor is only mounting panel and running conduit to feed garage. Homeowner wiring shop. His permit # is ELE20-02137
ELE20-00596 Rough-In Permanent Service7/9/20207/10/20207/10/2020 11:08:38 AMAPASS
Phone #: ###-#### Inspection requested via web by james mair Ok cover grd work only between 2 buildings, no service.
ELE20-02027 Final7/3/20207/10/20207/10/2020 10:11:38 AMAPASS
MAIN CONTACT - Levi Henry ###-####
On-site Blue Raven Technician: Mierins Rozentals ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting Ok final. Door does not quite open 90 degrees on combiner box, but door can easily be removed by pushing up. Mentioned to worker onsite that for future installs door needs to open atleast 90 degrees. 110.26(A)(2)
ELE20-02367 Electrical Rough-In7/10/20207/10/20207/10/2020 10:04:50 AMAPASS
Call 30 minutes before Phone #: ###-#### Inspection requested via web by Terry Scott Ok cover kitchen
ELE19-04952 Final7/8/20207/10/20207/10/2020 9:19:50 AMANH
Please contact Nash for questions Phone #: ###-#### Inspection requested via web by Bayley Beard Knocked on door 915 no answer. Talked to electrician about sheduling when access is available