ELE18-02829
| Final | 8/8/2018 | 8/8/2018 | 8/8/2018 2:05:49 PM | P | NR |
|
|
Was not supposed to be called in until 8/9/18 for final as per Phillip.
|
ELE18-02313
| Electrical Rough-In | 8/7/2018 | 8/8/2018 | 8/8/2018 1:28:38 PM | P | PASS |
|
|
We would like a light pole base inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover 3 lt poles E side.
|
ELE18-01733
| Permanent Service | 8/7/2018 | 8/8/2018 | 8/8/2018 11:25:16 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Barbara Szurgot Had contractor add a 2nd ground rod for each service.
|
ELE18-02988
| Permanent Service | 8/7/2018 | 8/8/2018 | 8/8/2018 11:24:43 AM | A | PASS |
|
|
Service and trench inspection Phone #: ###-#### Inspection requested via web by Barbara Szurgot Had contractor add a 2nd ground rod for each service. p/s o/h n ok
|
ELE18-02999
| Electrical Rough-In | 8/8/2018 | 8/8/2018 | 8/8/2018 11:02:48 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jesse Fuentes Ok cover enclosed patio.
|
ELE18-01558
| Electrical Rough-In | 8/7/2018 | 8/8/2018 | 8/8/2018 10:26:40 AM | A | PASS |
|
|
drop ceiling 4th floor in the hallways and the 3rd floor unit drop ceilings in the units Phone #: ###-#### Inspection requested via web by steve cooper Ok cover 4th floor hall, and 2nd floor unit ceilings. Junction box in ceiling 4th floor near E stairwell needs to be accessible upon final. Junction box was needed to fix heat tape that was cut. Also reminded electrician that a KO seal is needed for panel in rm 411.
|
ELE18-02016
| Final | 8/7/2018 | 8/8/2018 | 8/8/2018 10:01:09 AM | A | PASS |
|
|
Please contact Dustin Palmer. Phone #: ###-#### Inspection requested via web by Harvey Reyna Ok final recepts on front of stage, and storage area underneath with light that is a 3way.
|
ELE18-02080
| Final | 8/8/2018 | 8/8/2018 | 8/8/2018 9:25:32 AM | A | PASS |
|
|
general contractor will be there all day. Phone #: ###-#### Inspection requested via web by todd cline Ok final.
|
ELE18-02998
| Permanent Service | 8/7/2018 | 8/8/2018 | 8/8/2018 9:01:01 AM | A | PASS |
|
|
also need under ground looked at that''s going to feed existing panel location I should be in the area call me and I will come over. we are doing the same thing as last job on 18th. trying to get the service passed so we can finish frame up and properly secure mast. it is just temporarily supported at the moment. Phone #: ###-#### Inspection requested via web by Jay Hutchison Ok cover trench. Service o/h mast secured to allow remainder of stucture to be built. Once roofing is installed, mast will remain in place and secured as per code. p/s o/h n ok
|
ELE18-02839
| Final | 8/6/2018 | 8/8/2018 | 8/8/2018 7:34:04 AM | A | FAIL |
|
|
We have left plans on site Phone #: ###-#### Inspection requested via web by Ashley White No RI inspection requested. Bring components on site to verify UL listing.
|
ELE18-02147
| Electrical Rough-In | 8/7/2018 | 8/8/2018 | 8/7/2018 2:39:54 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by steve ragan Ok cover basement. Looked at on 8/7/18. Talked to homeowner on the phone and she gave me permission to access basement through back door of property.
|