ELE16-02941
| Electrical Rough-In | 9/8/2016 | 9/9/2016 | 9/9/2016 3:36:00 PM | P | PASS |
|
|
third and fourth floor inspection of Building Q Phone #: ###-#### Inspection requested via web by Bob Stephens For future buildings layout of outlets must follow the NEC as per Daryl Degrange roughin ok to cover.
|
ELE16-02906
| Rough-In Permanent Service | 9/6/2016 | 9/9/2016 | 9/9/2016 2:06:59 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Zane Robertson p/s u/g n ok
|
ELE16-02939
| Electrical Rough-In | 9/8/2016 | 9/9/2016 | 9/9/2016 2:06:30 PM | P | PASS |
|
|
pre-pipe only for solar Phone #: ###-#### Inspection requested via web by michael hunt rough in ok
|
ELE16-02545
| Electrical Rough-In | 9/9/2016 | 9/9/2016 | 9/9/2016 1:33:17 PM | P | PASS |
|
|
Peter Phone #: ###-#### rough in ok
|
ELE16-02873
| Electrical Rough-In | 9/6/2016 | 9/9/2016 | 9/9/2016 1:08:20 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Shawn Dulin rough in ok
|
ELE16-02067
| Permanent Service | 9/9/2016 | 9/9/2016 | 9/9/2016 12:39:20 PM | P | PASS |
|
|
Service energize inspection Phone #: ###-#### Inspection requested via web by Tye Thomas p/s ug n ok
|
ELE16-02946
| Final | 9/9/2016 | 9/9/2016 | 9/9/2016 12:36:41 PM | P | CANC |
|
|
Garage is in the back alleyway. Any questions please call David. Thank you. Phone #: ###-#### Inspection requested via web by Charmel Kubik
|
ELE16-02946
| Electrical Rough-In | 9/9/2016 | 9/9/2016 | 9/9/2016 12:36:16 PM | P | PASS |
|
|
Garage is in the back alleyway. Any questions please call David. Thank you. Phone #: ###-#### Inspection requested via web by Charmel Kubik rough in ok
|
ELE16-02940
| Electrical Rough-In | 9/8/2016 | 9/9/2016 | 9/9/2016 11:52:36 AM | A | PASS |
|
|
Altenergy Jesse ###-#### is my contact, job is done on my end. Phone #: ###-#### Inspection requested via web by Andy Derrick rough in ok
|
ELE16-02855
| Final | 9/8/2016 | 9/9/2016 | 9/9/2016 11:50:25 AM | A | CANC |
|
|
I will call in the morning and schedule a time to meet you onsite. Phone #: ###-#### Inspection requested via web by Matthew Dunay not completed
|
ELE16-02495
| Final | 9/8/2016 | 9/9/2016 | 9/9/2016 11:35:09 AM | A | PASS |
|
|
Please call Gabe when you are on your way, ###-####. Thank You. Phone #: ###-#### Inspection requested via web by Clay Morgan final ok
|
ELE16-00876
| Final | 9/8/2016 | 9/9/2016 | 9/9/2016 11:20:51 AM | A | PASS |
|
|
you might have to use back slider entrance or man door if drive way looks stained thanks Phone #: ###-#### Inspection requested via web by Erick Baker corrections made final ok
|
ELE16-01361
| Electrical Rough-In | 9/8/2016 | 9/9/2016 | 9/9/2016 10:17:05 AM | A | PASS |
|
|
Mucho Phone #: ###-#### floor heat ok to cover
|
ELE16-02945
| Rough-In Permanent Service | 9/8/2016 | 9/9/2016 | 9/9/2016 10:16:40 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Neal Rumsey p/s u/g n ok
|
ELE16-01389
| Final | 9/8/2016 | 9/9/2016 | 9/9/2016 10:16:13 AM | A | PASS |
|
|
Call for access ###-#### Phone #: ###-#### Inspection requested via web by danny perrine final ok
|
ELE16-02930
| Rough-In Permanent Service | 9/8/2016 | 9/9/2016 | 9/9/2016 9:00:44 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk p/s u/g n ok
|
ELE16-02933
| Temporary Service | 9/8/2016 | 9/9/2016 | 9/9/2016 9:00:12 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk t/s u/g n ok
|
ELE16-02236
| Final | 9/8/2016 | 9/9/2016 | 9/9/2016 8:56:11 AM | A | PASS |
|
|
Garage code 1001E Phone #: ###-#### Inspection requested via web by Alan Lusk final ok
|
ELE16-02923
| Temporary Service | 9/7/2016 | 9/9/2016 | 9/9/2016 8:27:11 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rhonda Yoast t/s u/g n ok
|
ELE16-02944
| Temporary Service | 9/8/2016 | 9/9/2016 | 9/9/2016 8:19:55 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Darryn Coburn t/s ug n ok
|