ELE20-00217
| Permanent Service | 1/20/2020 | 1/22/2020 | 1/22/2020 2:34:20 PM | P | PASS |
|
|
Please call Mitch 30 minutes prior. Phone #: ###-#### Inspection requested via web by Mitch Whited...p/s o/h reconnect ok
|
ELE20-00247
| Final | 1/22/2020 | 1/22/2020 | 1/22/2020 2:22:03 PM | P | PASS |
|
|
Inspect a Transfer switch, for emergency generator power.
*I will be there.
Thank you, Lonnie Phone #: ###-#### Inspection requested via web by Lonnie Sorichta... labelling and connections complete...ok to final
|
ELE20-00247
| Electrical Rough-In | 1/21/2020 | 1/22/2020 | 1/22/2020 2:21:32 PM | P | PASS |
|
|
Inspect a Transfer switch, for emergency generator power.
*I will be there.
Thank you, Lonnie Phone #: ###-#### Inspection requested via web by Lonnie Sorichta...backfed generator power board from outside outlet...on surface in garage tied to chosen breakers...generator panel box labelled as per circuits fed...ok
|
ELE19-04850
| Final | 1/22/2020 | 1/22/2020 | 1/22/2020 12:59:43 PM | P | PASS |
|
|
Jay Phone #: ###-####...ok to final
|
ELE20-00246
| Electrical Rough-In | 1/21/2020 | 1/22/2020 | 1/22/2020 12:46:06 PM | P | PASS |
|
|
Thank you Phone #: ###-#### Inspection requested via web by David Kubik... new service...verify GFCI protection and bonding for tub at needed final inspection
|
ELE20-00246
| Permanent Service | 1/22/2020 | 1/22/2020 | 1/22/2020 12:44:49 PM | P | PASS |
|
|
Thank you Phone #: ###-#### Inspection requested via web by David Kubik... p/s o/h reconnect ok
|
ELE20-00243
| Temporary Service | 1/21/2020 | 1/22/2020 | 1/22/2020 12:20:22 PM | P | PASS |
|
|
Corey Hayes ###-#### Phone #: ###-#### Inspection requested via web by Jeremy Cloud...t/s o/h n ok
|
ELE19-04654
| Final | 1/15/2020 | 1/22/2020 | 1/22/2020 11:51:20 AM | P | PASS |
|
|
electrician not onsite, Matt Jones ###-####. can call office for details. Phone #: ###-#### Inspection requested via web by Matthew White.. new cans ok
|
ELE20-00241
| Conference | 1/21/2020 | 1/22/2020 | 1/22/2020 10:57:38 AM | A | PASS |
|
|
Robert Phone #: ###-####... discussed adding 100A sub panel in garage on surface next to existing 200A...running 3 - 240V circuits on surface to wood working equipment... went over strapping/supporting of conduit/pvc sch 80 on surface of garage...homeowner very competent
|
ELE20-00057
| Rough-In Permanent Service | 1/21/2020 | 1/22/2020 | 1/22/2020 10:09:55 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rodney Monroe... rough-in ok p/s u/g new ok
|
ELE20-00162
| Rough-In Permanent Service | 1/21/2020 | 1/22/2020 | 1/22/2020 9:27:48 AM | A | PASS |
|
|
This is for a service inspection. Access it from inside the apartment parking lot. Phone #: ###-#### Inspection requested via web by Sherry Allen...p/s u/g new ok
|
ELE19-03967
| Electrical Rough-In | 1/22/2020 | 1/22/2020 | 1/22/2020 9:08:30 AM | A | PASS |
|
|
Wall cover. Rigo is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen...wall cover complete
|
ELE20-00249
| Rough-In Permanent Service | 1/22/2020 | 1/22/2020 | 1/22/2020 8:31:04 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Neal Rumsey... rough-in ok...p/s u/g new ok
|
ELE20-00194
| Permanent Service | 1/20/2020 | 1/22/2020 | 1/21/2020 8:36:32 PM | A | CANC |
|
|
Upgrade of 100A service to 200a all-in one for furnace in crawl Any questions contact Jack Phone #: ###-#### >> Inspection requested via web by Jack Bernard Inspection cancelled from web by: Jack Bernard
|
ELE20-00244
| Rough-In Permanent Service | 1/21/2020 | 1/22/2020 | 1/21/2020 3:56:14 PM | P | CANC |
|
|
please call ahead Phone #: ###-#### >> Inspection requested via web by Kyle Dillon Inspection cancelled from web by: Kyle Dillon
|